Difference between revisions of "Halls A and C Spectrometer Support Group Whiteboard"

From Hall A Wiki
Jump to: navigation, search
(Priority Items)
(21 intermediate revisions by 3 users not shown)
Line 1: Line 1:
 
== Priority Items ==
 
== Priority Items ==
 +
 +
Readout for LCW pressure sensors added at end of beamline walkway (not started)
 +
 +
Check if optocoupler is missing in LQ2 FuG - Looked for this. Didn't see one on the main boards, but realized as I am writing this, maybe it was for the interface for remote polarity switching? --Ellen
  
 
Buy and replace MFCs in old FPP mixing system - MFCs on order
 
Buy and replace MFCs in old FPP mixing system - MFCs on order
  
Install VVU on SBB power supply - VVU ordered
+
Replace air compressor in Hall A Gas Shed - asked for quote
  
Install spring washers on SBB and BB busbars and connections
+
Gas manifolds for GEM gas cylinders (started)
  
Readout for LCW pressure sensors added at end of beamline walkway (not started)
+
Hall C Moller: setup new chiller, modify bertha, get new helium lines installed when they come in and test magnet cooldown
  
Fix LCW leak in LD1 Dynapower
+
Nitrogen supply for GEM gas cylinder valves (Clippard valves and cylinder controller) (not started)
  
Check if optocoupler is missing in LQ2 FuG - Looked for this. Didn't see one on the main boards, but realized as I am writing this, maybe it was for the interface for remote polarity switching? --Ellen
+
Gas mix controller and MFCs for GEM detectors (not started)
  
Adjust Ar/CO2 mix ratio in old FPP controller to match the pre-mix used for GEMs
+
Determine 100% liquid level set point/Hall C magnets.
  
Replace air compressor in Hall A Gas Shed
+
Warm up HB.
  
Find video cables from hall in the CH
+
Add "T's" and pump out ports to HMS magnet vacuum gauge ports.
  
Gas manifolds for GEM gas cylinders (started)
+
Add ventilation to SHMS Dipole flow meter shielding.
  
Nitrogen supply for GEM gas cylinder valves (Clippard valves and cylinder controller) (not started)
+
Find 4 atmos leak in Hall C.
  
Gas mix controller and MFCs for GEM detectors (not started)
+
Move ozone meters from VME to PI.
 +
 
 +
Add fan to beamline side lead (HB)
 +
 
 +
Modify HMS lead heaters, add perforated sheets up stream and add a perforated box downstream to fit heater.
  
 
== Would Be Good To Do Items ==
 
== Would Be Good To Do Items ==
Line 37: Line 45:
 
Calibrate and op-check spare warm return valves for Hall C.
 
Calibrate and op-check spare warm return valves for Hall C.
  
<s>Setup controls9</s> Done
+
Add bypass switch for SHMS UPS - Switch ordered
  
Hall C Moller: setup new chiller, repair compressor, modify bertha
+
== Do We Still Need To Do These? ==
  
<s>Add bypass switch for SHMS UPS</s> Replacement UPS should come with a bypass switch
+
== Possible Future Items ==
  
== PARTS ORDER LIST FOR 1 OCT ==
+
Remote reset for Hall C spectrometer motion (maybe next year)
  
-2 wire cable,
+
Install new liquid level meters on SHMS- Install done, waiting on software and LN2 probe cal to go live (need Steven).
ferrules,
+
\# 6 hardware
+
  
== Do We Still Need To Do These? ==
+
Fix LCW leak in LD1 Dynapower
  
Test LQ2 FuG with new polarity reversal switch.
+
Replace pressure sensors on the Hall A Ethane manifold
  
Mount Left Shield House temperature readout in CH
+
Replace ground fault module in LQ1 power supply
  
Find and connect NMR cables in CH
+
Test LQ2 FuG with new polarity reversal switch.
  
 
Swap out MFCs in VDC mixing system
 
Swap out MFCs in VDC mixing system
 
== Possible Future Items ==
 
 
Remote reset for Hall C spectrometer motion (maybe next year)
 
 
Install new liquid level meters on SHMS- Install done, waiting on software and LN2 probe cal to go live (need Steven).
 

Revision as of 17:16, 31 March 2022

Priority Items

Readout for LCW pressure sensors added at end of beamline walkway (not started)

Check if optocoupler is missing in LQ2 FuG - Looked for this. Didn't see one on the main boards, but realized as I am writing this, maybe it was for the interface for remote polarity switching? --Ellen

Buy and replace MFCs in old FPP mixing system - MFCs on order

Replace air compressor in Hall A Gas Shed - asked for quote

Gas manifolds for GEM gas cylinders (started)

Hall C Moller: setup new chiller, modify bertha, get new helium lines installed when they come in and test magnet cooldown

Nitrogen supply for GEM gas cylinder valves (Clippard valves and cylinder controller) (not started)

Gas mix controller and MFCs for GEM detectors (not started)

Determine 100% liquid level set point/Hall C magnets.

Warm up HB.

Add "T's" and pump out ports to HMS magnet vacuum gauge ports.

Add ventilation to SHMS Dipole flow meter shielding.

Find 4 atmos leak in Hall C.

Move ozone meters from VME to PI.

Add fan to beamline side lead (HB)

Modify HMS lead heaters, add perforated sheets up stream and add a perforated box downstream to fit heater.

Would Be Good To Do Items

Remove actuators from right arm magnets. (Dipole/Q3 complete)

clean up R-arm supply platform

clean up L-arm supply platform

HMS/SHMS Heater and fan changes, fixes, upgrades etc.

Calibrate and op-check spare warm return valves for Hall C.

Add bypass switch for SHMS UPS - Switch ordered

Do We Still Need To Do These?

Possible Future Items

Remote reset for Hall C spectrometer motion (maybe next year)

Install new liquid level meters on SHMS- Install done, waiting on software and LN2 probe cal to go live (need Steven).

Fix LCW leak in LD1 Dynapower

Replace pressure sensors on the Hall A Ethane manifold

Replace ground fault module in LQ1 power supply

Test LQ2 FuG with new polarity reversal switch.

Swap out MFCs in VDC mixing system