Re-install crash buttons in Hall A Counting Room - RQ1 button for BB and new one for SBS supply
+
== Priority Items ==
  
Swap out MFCs in VDC mixing system
+
Replace PLC relay card on SHMS Dipole - spare card is on the 2nd floor
  
Remove three Oxford power supplies from HMS
+
Install 230V -> 115V transformers for +/-15V supplies dying in Hall C Danfysik supplies - transformers ordered
  
<s>HMS Q2 lead voltage drops</s> Done
+
Readout for LCW pressure sensors added at end of beamline walkway (not started)
  
Heaters for SHMS magnet flags.
+
Replace air compressor in Hall A Gas Shed - ordered - need to remove old compressor and dryer.
  
Hall A cooldown.
+
Gas manifolds for GEM gas cylinders (started)
  
Heaters for HMS magnet flags-Heaters-modifications to guards complete, heaters installed.  Waiting on controller.
+
Nitrogen supply for GEM gas cylinder valves (Clippard valves and cylinder controller) (not started)
  
Help Brad re-configure the DAQ rack in Counting Room C
+
Gas mix controller and MFCs for GEM detectors (not started)
  
Swap out CAEN HV crate in Counting Room C
+
Add "T's" and pump out ports to HMS magnet vacuum gauge ports.-Steve didn't want work done.
  
Controls for SBS corrector coils
+
Move ozone meters from VME to PI.
  
Re-tap the SBS supply main transformer for full power
+
== Would Be Good To Do Items ==
  
re-install ground fault detector in LQ1 supply - requires configuration of module
+
Remove actuators from right arm magnets. (Dipole/Q3 complete)
 
+
connect power and LCW to BB supply on R-arm platform
+
 
+
Replace air compressor in Hall A Gas Shed
+
 
+
re-locate displays for hacweb11 and 14
+
  
 
clean up R-arm supply platform
 
clean up R-arm supply platform
Line 33: Line 27:
 
clean up L-arm supply platform
 
clean up L-arm supply platform
  
Install new liquid level meters on SHMS- Install done, waiting on software and LN2 probe cal to go live.
+
Build new controller for testing and calibration warm return valves for Hall C
 
+
Remove actuators from right arm magnets. (Dipole complete)
+
 
+
<s>HMS supply control boxes into the Shield Hut</s> Done
+
 
+
Gas mix controller for GEM detectors
+
  
<s>Fix relay box for HMS counting room E-Stops</s> Done
+
Build local valve control boxes with local read out.
  
Re-locate NDX detectors in Hall A - one in DAQ bunker and the other in BB GEM bunker
+
op check/repair hall C vacuum gauges.
  
Readout for LCW pressure sensors added at end of beamline walkway
+
Re-route the Danfysik extension cables inside the HMS hut - get the excess off the floor
  
Remote reset for Hall C spectrometer motion
+
Cut and install poly shielding around HVAC controls on the Right HRS
  
Install new quench protection boards in Hall A LD1
+
== Do We Still Need To Do These? ==
  
<s>Reconnect Magnet On signs to the HMS supplies</s> Done
+
== Possible Future Items ==
  
Hall A moller re-install: target install and survey, compressor and chiller clean up and setup, testing
+
Remote reset for Hall C spectrometer motion (maybe next year)

Revision as of 12:18, 12 August 2022

Priority Items

Replace PLC relay card on SHMS Dipole - spare card is on the 2nd floor

Install 230V -> 115V transformers for +/-15V supplies dying in Hall C Danfysik supplies - transformers ordered

Readout for LCW pressure sensors added at end of beamline walkway (not started)

Replace air compressor in Hall A Gas Shed - ordered - need to remove old compressor and dryer.

Gas manifolds for GEM gas cylinders (started)

Nitrogen supply for GEM gas cylinder valves (Clippard valves and cylinder controller) (not started)

Gas mix controller and MFCs for GEM detectors (not started)

Add "T's" and pump out ports to HMS magnet vacuum gauge ports.-Steve didn't want work done.

Move ozone meters from VME to PI.

Would Be Good To Do Items

Remove actuators from right arm magnets. (Dipole/Q3 complete)

clean up R-arm supply platform

clean up L-arm supply platform

Build new controller for testing and calibration warm return valves for Hall C

Build local valve control boxes with local read out.

op check/repair hall C vacuum gauges.

Re-route the Danfysik extension cables inside the HMS hut - get the excess off the floor

Cut and install poly shielding around HVAC controls on the Right HRS

Do We Still Need To Do These?

Possible Future Items

Remote reset for Hall C spectrometer motion (maybe next year)