== Priority Items ==
 
== Priority Items ==
  
Readout for LCW pressure sensors added at end of beamline walkway (not started)
+
Install 2:1 transformers in SHMS Danfysik supplies
  
Check if optocoupler is missing in LQ2 FuG - Looked for this. Didn't see one on the main boards, but realized as I am writing this, maybe it was for the interface for remote polarity switching? --Ellen
+
Install pressure sensor in warm return in ESR
  
Buy and replace MFCs in old FPP mixing system - MFCs on order
+
Replace/repair dead MAGNET ON signs in Hall C
  
Replace air compressor in Hall A Gas Shed - ordered - need to remove old compressor and dryer.
+
Some of the SBS magnet bus bars have been running hot. Do we need to re-torque them?
 +
 
 +
Readout for LCW pressure sensors added at end of beamline walkway (not started)
  
 
Gas manifolds for GEM gas cylinders (started)
 
Gas manifolds for GEM gas cylinders (started)
 
Replacement for EEL two cylinder gas cart - ordered, waiting on delivery
 
 
Hall C Moller: setup new chiller, modify bertha, get new helium lines installed when they come in and test magnet cooldown
 
  
 
Nitrogen supply for GEM gas cylinder valves (Clippard valves and cylinder controller) (not started)
 
Nitrogen supply for GEM gas cylinder valves (Clippard valves and cylinder controller) (not started)
Line 19: Line 17:
 
Gas mix controller and MFCs for GEM detectors (not started)
 
Gas mix controller and MFCs for GEM detectors (not started)
  
Warm up HB.
+
Add "T's" and pump out ports to HMS magnet vacuum gauge ports.-Steve didn't want work done.
 
+
Add "T's" and pump out ports to HMS magnet vacuum gauge ports.
+
 
+
Add ventilation to SHMS Dipole flow meter shielding.
+
 
+
Find 4 atmos leak in Hall C.
+
 
+
Move ozone meters from VME to PI.
+
 
+
Add fan to beamline side lead (HB)
+
 
+
Modify HMS lead heaters, add perforated sheets up stream and add a perforated box downstream to fit heater.
+
  
 
== Would Be Good To Do Items ==
 
== Would Be Good To Do Items ==
Line 41: Line 27:
 
clean up L-arm supply platform
 
clean up L-arm supply platform
  
HMS/SHMS Heater and fan changes, fixes, upgrades etc.
+
Build new controller for testing and calibration warm return valves for Hall C
 +
 
 +
Build local valve control boxes with local read out.
 +
 
 +
op check/repair hall C vacuum gauges.
  
Calibrate and op-check spare warm return valves for Hall C.
+
Re-route the Danfysik extension cables inside the HMS hut - get the excess off the floor
  
Add bypass switch for SHMS UPS - Switch ordered
+
Cut and install poly shielding around HVAC controls on the Right HRS
  
 
== Do We Still Need To Do These? ==
 
== Do We Still Need To Do These? ==

Latest revision as of 18:08, 21 November 2022

Priority Items

Install 2:1 transformers in SHMS Danfysik supplies

Install pressure sensor in warm return in ESR

Replace/repair dead MAGNET ON signs in Hall C

Some of the SBS magnet bus bars have been running hot. Do we need to re-torque them?

Readout for LCW pressure sensors added at end of beamline walkway (not started)

Gas manifolds for GEM gas cylinders (started)

Nitrogen supply for GEM gas cylinder valves (Clippard valves and cylinder controller) (not started)

Gas mix controller and MFCs for GEM detectors (not started)

Add "T's" and pump out ports to HMS magnet vacuum gauge ports.-Steve didn't want work done.

Would Be Good To Do Items

Remove actuators from right arm magnets. (Dipole/Q3 complete)

clean up R-arm supply platform

clean up L-arm supply platform

Build new controller for testing and calibration warm return valves for Hall C

Build local valve control boxes with local read out.

op check/repair hall C vacuum gauges.

Re-route the Danfysik extension cables inside the HMS hut - get the excess off the floor

Cut and install poly shielding around HVAC controls on the Right HRS

Do We Still Need To Do These?

Possible Future Items

Remote reset for Hall C spectrometer motion (maybe next year)