Difference between revisions of "Halls A and C Spectrometer Support Group Whiteboard"
Line 5: | Line 5: | ||
Remove three Oxford power supplies from HMS | Remove three Oxford power supplies from HMS | ||
− | HMS Q2 lead voltage drops | + | {{strikethrough|HMS Q2 lead voltage drops} Done |
Heaters for SHMS magnet flags. | Heaters for SHMS magnet flags. | ||
Line 37: | Line 37: | ||
Remove actuators from right arm magnets. (Dipole complete) | Remove actuators from right arm magnets. (Dipole complete) | ||
− | HMS supply control boxes into the Shield Hut | + | {{strikethrough|HMS supply control boxes into the Shield Hut}} Done |
Gas mix controller for GEM detectors | Gas mix controller for GEM detectors | ||
− | Fix relay box for HMS counting room E-Stops | + | {{strikethrough|Fix relay box for HMS counting room E-Stops}} Done |
Re-locate NDX detectors in Hall A - one in DAQ bunker and the other in BB GEM bunker | Re-locate NDX detectors in Hall A - one in DAQ bunker and the other in BB GEM bunker |
Revision as of 11:26, 22 July 2021
Re-install crash buttons in Hall A Counting Room - RQ1 button for BB and new one for SBS supply
Swap out MFCs in VDC mixing system
Remove three Oxford power supplies from HMS
{{strikethrough|HMS Q2 lead voltage drops} Done
Heaters for SHMS magnet flags.
Hall A cooldown.
Heaters for HMS magnet flags-Heaters-modifications to guards complete, heaters installed. Waiting on controller.
Help Brad re-configure the DAQ rack in Counting Room C
Swap out CAEN HV crate in Counting Room C
Controls for SBS corrector coils
Re-tap the SBS supply main transformer for full power
re-install ground fault detector in LQ1 supply - requires configuration of module
connect power and LCW to BB supply on R-arm platform
Replace air compressor in Hall A Gas Shed
re-locate displays for hacweb11 and 14
clean up R-arm supply platform
clean up L-arm supply platform
Install new liquid level meters on SHMS- Install done, waiting on software and LN2 probe cal to go live.
Remove actuators from right arm magnets. (Dipole complete)
Gas mix controller for GEM detectors
Re-locate NDX detectors in Hall A - one in DAQ bunker and the other in BB GEM bunker
Readout for LCW pressure sensors added at end of beamline walkway
Remote reset for Hall C spectrometer motion
Install new quench protection boards in Hall A LD1