Difference between revisions of "Meeting 2022 03 2"

From Hall A Wiki
Jump to: navigation, search
(Near term work plan (all))
(Near term work plan (all))
Line 9: Line 9:
 
* Hoping for end of April to install HV dividers on BB.
 
* Hoping for end of April to install HV dividers on BB.
 
* [https://docs.google.com/spreadsheets/d/1QGkJZEgs3Uel5TfvR5iCwstGbNRv8rCM_hfFXXwRf2o/edit?usp=sharing BB APV status]
 
* [https://docs.google.com/spreadsheets/d/1QGkJZEgs3Uel5TfvR5iCwstGbNRv8rCM_hfFXXwRf2o/edit?usp=sharing BB APV status]
 +
** 10 APVs with missing strips.
 +
** ~400 strips missing (out of 30720)
 +
** Only 2 APVs near the center of the acceptance, about 60 strips.
 
* Need 1 layer with HV divider upgrade for the SBS stack.
 
* Need 1 layer with HV divider upgrade for the SBS stack.
 
* HV divider upgrade for INFN GEMs
 
* HV divider upgrade for INFN GEMs

Revision as of 10:48, 2 March 2022

GMn GEM commissioning Meetings: WEDNESDAY 10:30am - 11:30am

Link to all previous meetings: GMn GEM Commissioning Meeting

Please use sbs_gems mailing list for plots/communications and HALOG entries relevant to GEMs!


Near term work plan (all)

  • Hoping for end of April to install HV dividers on BB.
  • BB APV status
    • 10 APVs with missing strips.
    • ~400 strips missing (out of 30720)
    • Only 2 APVs near the center of the acceptance, about 60 strips.
  • Need 1 layer with HV divider upgrade for the SBS stack.
  • HV divider upgrade for INFN GEMs
  • Brad: update on date for install of SBS GEMs in Hall A.
    • Need 2-3 months for APVs for 10th SBS layer.
    • Need 1 week to install all dividers on BB GEMs and test.

Update on BB GEMs(Sean, Ezekiel, Holly, Anu)

Update on UVa GEM layers for GEn-RP (Anu, John, Thir)

  • APV inventory

Update on INFN GEM layers for GEn-RP (Ezekiel, Holly, Evaristo)

DAQ updates (Ben, Bryan, Alex)

  • schematic of setup?
  • FIR filter?
  • Update on: need 2 DC working in Hall A