===  Near term work plan (all) ===
 
===  Near term work plan (all) ===
* Hoping for end of April to install HV dividers on BB.
+
* Installation of HV dividers on BB: April 18 for 3 weeks (3d/layer + 3 float days).
 
* [https://docs.google.com/spreadsheets/d/1QGkJZEgs3Uel5TfvR5iCwstGbNRv8rCM_hfFXXwRf2o/edit?usp=sharing BB APV status]
 
* [https://docs.google.com/spreadsheets/d/1QGkJZEgs3Uel5TfvR5iCwstGbNRv8rCM_hfFXXwRf2o/edit?usp=sharing BB APV status]
 
** 10 APVs with missing strips.
 
** 10 APVs with missing strips.
Line 19: Line 19:
  
 
===  Update on BB GEMs(Sean, Ezekiel, Holly, Anu) ===
 
===  Update on BB GEMs(Sean, Ezekiel, Holly, Anu) ===
* [https://hallaweb.jlab.org/wiki/images/5/51/Neg_pulse_tracking_3_1_22.pdf Negative tracking results] - Sean
+
* [https://sbs.jlab.org/DocDB/0001/000167/001/Neg_pulse_tracking_3_1_22.pdf Negative tracking results] - Sean
 
** Full plots in the HALOG, https://logbooks.jlab.org/entry/3986717
 
** Full plots in the HALOG, https://logbooks.jlab.org/entry/3986717
  
 
=== Update on UVa GEM layers for GEn-RP (Anu, John, Thir) ===
 
=== Update on UVa GEM layers for GEn-RP (Anu, John, Thir) ===
* APV inventory
+
* [https://docs.google.com/presentation/d/1SzAx1r8JWTnHIDk4mqiOYauErR2q3ivpKURuwB_PbRo/edit#slide=id.g117dd12dc63_0_0 EEL 125 GEM DAQ updates] -- will present next week
  
 
=== Update on INFN GEM layers for GEn-RP (Ezekiel, Holly, Evaristo) ===
 
=== Update on INFN GEM layers for GEn-RP (Ezekiel, Holly, Evaristo) ===

Latest revision as of 21:00, 2 March 2022

GMn GEM commissioning Meetings: WEDNESDAY 10:30am - 11:30am

Link to all previous meetings: GMn GEM Commissioning Meeting

Please use sbs_gems mailing list for plots/communications and HALOG entries relevant to GEMs!


Near term work plan (all)

  • Installation of HV dividers on BB: April 18 for 3 weeks (3d/layer + 3 float days).
  • BB APV status
    • 10 APVs with missing strips.
    • ~400 strips missing total (out of 30,720)
    • Only 2 APVs near the center of the acceptance, about 60 strips.
  • Need 1 layer with HV divider upgrade for the SBS stack.
  • HV divider upgrade for INFN GEMs
  • Brad: update on date for install of SBS GEMs in Hall A.
    • Need 2-3 months for APVs for 10th SBS layer.
    • Need 1 week to install all dividers on BB GEMs and test.

Update on BB GEMs(Sean, Ezekiel, Holly, Anu)

Update on UVa GEM layers for GEn-RP (Anu, John, Thir)

Update on INFN GEM layers for GEn-RP (Ezekiel, Holly, Evaristo)

DAQ updates (Ben, Bryan, Alex)

  • schematic of setup?
  • FIR filter?
  • Update on: need 2 DC working in Hall A