− | * | + | * Installation of HV dividers on BB: April 18 for 3 weeks (3d/layer + 3 float days). |
* [https://docs.google.com/spreadsheets/d/1QGkJZEgs3Uel5TfvR5iCwstGbNRv8rCM_hfFXXwRf2o/edit?usp=sharing BB APV status] | * [https://docs.google.com/spreadsheets/d/1QGkJZEgs3Uel5TfvR5iCwstGbNRv8rCM_hfFXXwRf2o/edit?usp=sharing BB APV status] | ||
** 10 APVs with missing strips. | ** 10 APVs with missing strips. | ||
Line 19: | Line 19: | ||
=== Update on BB GEMs(Sean, Ezekiel, Holly, Anu) === | === Update on BB GEMs(Sean, Ezekiel, Holly, Anu) === | ||
− | * [https:// | + | * [https://sbs.jlab.org/DocDB/0001/000167/001/Neg_pulse_tracking_3_1_22.pdf Negative tracking results] - Sean |
** Full plots in the HALOG, https://logbooks.jlab.org/entry/3986717 | ** Full plots in the HALOG, https://logbooks.jlab.org/entry/3986717 | ||
=== Update on UVa GEM layers for GEn-RP (Anu, John, Thir) === | === Update on UVa GEM layers for GEn-RP (Anu, John, Thir) === | ||
− | * | + | * [https://docs.google.com/presentation/d/1SzAx1r8JWTnHIDk4mqiOYauErR2q3ivpKURuwB_PbRo/edit#slide=id.g117dd12dc63_0_0 EEL 125 GEM DAQ updates] -- will present next week |
=== Update on INFN GEM layers for GEn-RP (Ezekiel, Holly, Evaristo) === | === Update on INFN GEM layers for GEn-RP (Ezekiel, Holly, Evaristo) === |
Latest revision as of 21:00, 2 March 2022
GMn GEM commissioning Meetings: WEDNESDAY 10:30am - 11:30am
Link to all previous meetings: GMn GEM Commissioning Meeting
Please use sbs_gems mailing list for plots/communications and HALOG entries relevant to GEMs!
Contents
Near term work plan (all)
- Installation of HV dividers on BB: April 18 for 3 weeks (3d/layer + 3 float days).
- BB APV status
- 10 APVs with missing strips.
- ~400 strips missing total (out of 30,720)
- Only 2 APVs near the center of the acceptance, about 60 strips.
- Need 1 layer with HV divider upgrade for the SBS stack.
- HV divider upgrade for INFN GEMs
- Brad: update on date for install of SBS GEMs in Hall A.
- Need 2-3 months for APVs for 10th SBS layer.
- Need 1 week to install all dividers on BB GEMs and test.
Update on BB GEMs(Sean, Ezekiel, Holly, Anu)
- Negative tracking results - Sean
- Full plots in the HALOG, https://logbooks.jlab.org/entry/3986717
Update on UVa GEM layers for GEn-RP (Anu, John, Thir)
- EEL 125 GEM DAQ updates -- will present next week
Update on INFN GEM layers for GEn-RP (Ezekiel, Holly, Evaristo)
DAQ updates (Ben, Bryan, Alex)
- schematic of setup?
- FIR filter?
- Update on: need 2 DC working in Hall A