===  Update on BB GEMs ===
 
===  Update on BB GEMs ===
* Setting up the individual channel power supply for UV layer 0.
+
* Individual channel power supply pedestal tested on UV layer 0.
* Pedestal test on Thursday to look at noise level.
+
* Set to 2000V, and all pedestals look normal, https://logbooks.jlab.org/entry/4006529
  
 
===  Common Mode Algorithms ===
 
===  Common Mode Algorithms ===

Latest revision as of 09:23, 29 June 2022

GMn GEM commissioning Meetings: WEDNESDAY 10:30am - 11:30am

Link to all previous meetings: GMn GEM Commissioning Meeting

Please use sbs_gems mailing list for plots/communications and HALOG entries relevant to GEMs!


Near term work plan

Update on INFN GEM layers for GEn-RP

  • Ran up a new divider on the front layer GEM of the inline stack. Verified temperature and V/I consistent with divider run-up with no GEM.
  • Currently in Hall. Plan to install new dividers on upstream-most layer while we can easily access. Will need sliding platform to remove the layer to install the new dividers on the second layer.

Update on UVa GEM layers for GEn-RP

  • Inline stack is in the Hall!

Update on BB GEMs

Common Mode Algorithms

DAQ updates (Ben, Bryan, Alex)

  • schematic of setup?
  • FIR filter?