Parasitic Production Run Plan R-HRS 48.75 degrees
From Hall A Wiki
Proton Elastic Kinematics
* If you need to increase the spectrometer momentum setting, make sure you cycle Q2 and Q3 as per the cycling procedure. * Elastic electron rates assume 15 μA on 15 cm LH2 target, 5 mSr acceptance. * Use the following prescale factors: ps1=1, ps2=1, ps3=1, ps8=100. All other triggers should have zero prescale factor. * For the optics pointing run, decrease the spectrometer momentum to 0.85 GeV/c. The right dipole will need about 1.5 hours to settle. * Take one hour on the optics target. * After the optics run is completed, then increase the spectrometer momentum back to the elastic setting.
Make sure to cycle the right Q2 and Q3 when increasing the momentum. * The 15 cm dummy runs need to be taken at the elastic setting. So keep the momentum as is for this run. * A GMp expert will check the data quality.
- 4th Pass (Ebeam = 8.5 GeV) Time estimate: 19 days @ 15 μA
Target | Raster | Ebeam [GeV] | P0 [GeV/c] | θe [deg] | Q2 [GeV2] | Electron Rate [Hz] at 15 μA | PAC days at 15 μA |
15 cm LH2 | 2 x 2 mm2 | 8.517 | 1.804 | 53.47 | 12.56 | 0.011 | 19 (for 17k events) |
15 cm Dummy | 2 x 2 mm2 | 8.517 | 1.804 | 53.47 | 12.56 | ---- | 1 hour |
Single Carbon | Off | 8.517 | 0.85 | 53.47 | 5.81 | 0.83 | 1 hour (for 3k events) |
- 5th Pass (Ebeam = 10.6 GeV) Time estimate: 22 days @ 15 μA
Target | Raster | Ebeam [GeV] | P0 [GeV/c] | θe [deg] | Q2 [GeV2] | Electron Rate [Hz] at 15 μA | PAC days at 15 μA |
15 cm LH2 | 2 x 2 mm2 | 10.617 | 1.896 | 53.25 | 16.33 | 0.002 | 22 (for 3.6k events) |
15 cm Dummy | 2 x 2 mm2 | 10.617 | 1.896 | 53.25 | 16.33 | ---- | 1 hour |
Single Carbon | Off | 10.617 | 0.85 | 53.25 | 7.24 | 0.69 | 1 hour (for 2.5k events) |