Preparations-DOE2014-Nov-Review

From Hall A Wiki
Revision as of 17:50, 31 October 2014 by Riordan (Talk | contribs) (Documentation for Reviewers)

Jump to: navigation, search

Documentation for Reviewers

  1. Seamus, Nilanga, Mahbub, Evaristo will be there both days.
  2. Todd will be available until 1pm.
  • Dry run on Oct 28th.
  1. Agenda for the dry run.
    1. Andrew Puckett, Physics Overview talk. pdf
    2. Mark Jones , Management talk.
    3. Thia Keppel ,Integration talk.
    4. Robin Wines, WBS 1 talk.
    5. Mahbub Khandaker, WBS 2 talk.
    6. Nilanga Liyanage, WBS 3 talk.
    7. Evaristo Cisbani, DAQ talk.
    8. Seamus Riordan, Background talk
    9. Mark Jones , Summary talk.
  2. Nilanga,Andrew, Seamus anytime after 8am.
  3. Mahbub is available 9:00 am - 12:00 pm .
  4. Evaristo is available until 2:30pm.

Response to DOE 2013 review report

  1. Final report from DOE Nov 2013 SBS review.
  2. DOE Nov 2013 recommendations with responses.
    1. Update the work flow for GEM module construction to include workforce (by type) required for each step.
      1. DOE SBS Nov 2013 monthly report included the work flow for GEM module construction to include workforce (by type).
      2. Sept 15th, Evaristo sent updated workflow and workforce plan
      3. Nilanga sent rear tracker work flow
    2. Develop a written Quality Assurance/test plan, including acceptance criteria for foils and assembled chambers that will be used for both UVa and INFN.
      1. Nilanga sent rear tracker Quality Assurance/test plan
      2. Evaristo sent front tracker Quality Assurance/test plan
    3. Conduct a background assessment for each experimental program that includes background rejection and signal efficiency as a function of trigger cuts, and present at the next review.
      1. Seamus is leading the effort.
      2. Draft report
    4. Develop a document describing the interface between the DAQ system and each of the 3 types of electronics (FADC, GEM, and FASTBUS) and present at the next review.
      1. Alexandre is leading the effort.
    5. Integration milestones for all equipment off-project, as well as key JLAB readiness and safety reviews, should be incorporated into the list of milestones. Provide updated list of milestones to DOE by January 1, 2014.
      1. List of milestones for off-project equipment dependencies was sent to DOE in Nov 2013 monthly report.
    6. Develop a Technical Specifications Document for all experimental components in the SBS program and present it at the next annual review.
      1. The general Template for the document.
      2. Mark Jones will coordinate information. Contacted the following people and set a deadline of Oct 6th.
      3. Detector Author Document
        CDET Mahbub Khandaker docx,pdf
        GRINCH Todd Averett docx,pdf
        HCAL Gregg Franklin docx,pdf
        ECAL Bogdan Wojtsekhowski docx,pdf
        GEM Front Tracker Evaristo Cisbani docx,pdf
        GEM Rear Tracker Nilanga Liyanage docx,pdf
        Polarized Helium target Gordon Cates
        Magnet 48D48 Bogdan Wojtsekhowski docx,pdf
        RICH Andrew Puckett docx,pdf
        Bigbite Scintillator Array John Annand docx,pdf
    7. Develop an integration plan for all experimental components (on and off project) needed for the SBS program, which includes activities, schedules and goals.
      1. Draft of the Integration Plan.
    8. Update the Research Management Plan to capture current plans for scientific effort needed to implement the project.
      1. Research Management Plan. Updated and sent to DOE in Jan 2014 Monthly report.
      2. Updated report<\li>
    9. The Project Management Plan should be updated to reflect changes in scope to the WBS components and evolving list of off-project equipment.
      1. Program Management Plan. Updated to include PMT based Coordinate Detector and list of off-project equipment dependencies and submitted to DOE in Jan 2014.