Line 19: | Line 19: | ||
# Prototype coils | # Prototype coils | ||
− | ## JLAB is holding up power supply and cable delivery | + | ## JLAB is holding up power supply and cable delivery - hopefully 1st week July |
## Going to ask Javier to get in touch with Jim Coleman | ## Going to ask Javier to get in touch with Jim Coleman | ||
− | ## water test requires some techs | + | ## water test requires some techs, booster pump |
## let us know if you need any "hands" | ## let us know if you need any "hands" | ||
# Sensitivity study | # Sensitivity study | ||
+ | ## problems with job submission discovered and fixed | ||
+ | ## sensitivities seem less restrictive than hybrid | ||
+ | ## maybe because field integral smaller | ||
+ | ## finish by end of summer | ||
+ | # Collimator simulations | ||
+ | ## Rakitha - shielding mass around target | ||
+ | ## Chandan and Cameron around collimators | ||
+ | ## Full range of radiation estimates by end of summer (site boundary, hall radiation, bkgds det plane) | ||
+ | ## Cameron moving to thesis | ||
# Collaboration meeting with Bluejeans calls | # Collaboration meeting with Bluejeans calls | ||
## possibly 2 half-day calls in July 16 and August 9 | ## possibly 2 half-day calls in July 16 and August 9 | ||
+ | # next teleconference on the 3rd | ||
Return to [[Teleconferences]]<br> | Return to [[Teleconferences]]<br> | ||
Return to [[MOLLER at 11 GeV E09-005]] | Return to [[MOLLER at 11 GeV E09-005]] |
Revision as of 10:22, 12 June 2018
previous meeting << >> following meeting
Logistic information
BlueJeans calling instructions: Toll-Free Number (U.S.& Canada): 888-240-2560 International toll number: 408-740-7256 Bluejeans CODE: 734 609 7559 Bluejeans link: https://bluejeans.com/7346097559
Agenda
- Prototype coil
- water pressure test results
- test plan
- Sensitivities update
- Collimator simulations update
Minutes
Attendance: Juliette, Sakib, KK, Ernie, Jim, Jason
- Prototype coils
- JLAB is holding up power supply and cable delivery - hopefully 1st week July
- Going to ask Javier to get in touch with Jim Coleman
- water test requires some techs, booster pump
- let us know if you need any "hands"
- Sensitivity study
- problems with job submission discovered and fixed
- sensitivities seem less restrictive than hybrid
- maybe because field integral smaller
- finish by end of summer
- Collimator simulations
- Rakitha - shielding mass around target
- Chandan and Cameron around collimators
- Full range of radiation estimates by end of summer (site boundary, hall radiation, bkgds det plane)
- Cameron moving to thesis
- Collaboration meeting with Bluejeans calls
- possibly 2 half-day calls in July 16 and August 9
- next teleconference on the 3rd