Transversity Collaboration Meeting

(May 08, 2008 at JLab L102/104)

 9:00-9:15    Hall A schedule update. -- Kees de Jager

 9:15-9:25    RICH update and installation plan. -- Evaristo Cisbani (.pdf)

 9:25-9:45    BigBite hardware for transversity.Installation plan for May. -- Doug Higinbotham

 9:45-10:00     BigBite gas Cherenkov progress. -- Brad Sawatzky

 10:00-10:15    Issues related to Low-Q2-ep experiment in May. -- Ron Gilman

 10:15-10:45     Discussions on May test run, a plan of actions. -- Xiaodong Jiang

 10:45-10:55    -- coffee break---

 10:55-11:10    Transversity trigger/DAQ, preparation for May test run. -- Kalyan Allada (.pdf)

 11:10-11:25    Issues on beam helicity signal. -- Bob Michaels (.pdf)

 11:25-11:40    chamber1+chamber2 performance during pi0 run.-- Xin Qian (.pdf)

 11:40-11:55    HRS detector update for transversity.-- Vincent Sulkosky (.pdf)

 11:55-12:10   BigBite software. -- Ole Hansen (.pdf)

 12:10-12:25    BigBite optics study from pi0-experiment data.-- Jin Huang (.pdf)

 12:25-13:30    -- Lunch break --

 13:30-13:45    BigBite related design. Doug Higinbotham discussions: major BigBite items left. -- Al Gavalya

 13:45-14:15    Polarized target design and discussions. -- Al Gavalya, J.P. Chen

 14:15-14:30    Target lab progress -- Chiranjib Dutta(.pdf)

 14:30-15:00    A plan of target installation.-- Jian-Ping Chen  15:00-15:30    Happex lumi-monitors. Beam charge feedback. Integration into transversity DAQ. -- Dustin McNulty

 15:30-15:40    --Coffee break--

 15:40-16:00    Progress on target spin-fip and integration into DAQ. -- Jin Huang

 16:00-16:30    Planning for summer installation:
           i. BigBite hardware, DAQ.
           ii. BigBite detector shielding.
           iii. HRS detector installation, S2M+A1+RICH.
           iv. Target magnet coil installation, field measurements.
           v. Target work and major tests in the hall.

 16:30-17:30   A summary of major milestone check. -- Xiaodong Jiang
           Discussions of manpower/responsibilities and collaboration issues

 17:30    -- adjourn --