Next: Independent Verification - Hall A
Up: Control of Equipment and
Previous: Control of Equipment and
The HRS superconducting magnets require special monitoring and control
procedures.
The ``Operational Safety Procedures for Hall A" containing these procedures
are located on the
Hall A console next to the magnet control screens/keyboards which have been
made remote to
the Hall A counting house. The instructions will enable the shift personnel
to due routine
operation of the magnets during Hall A commissioning. In addition, there
are a set of nine
large labeled red emergency shut down ``crash" buttons and two key switches
in the center of
the Hall A control room console.
The buttons have the following functions:
- 1.
- Emergency Accelerator Shutdown (activated when beam is enabled for
Hall A).
- 2.
- Emergency power supply shutdown for Electron HRS quadrupole Q1.
- 3.
- Emergency power supply shutdown for Electron HRS quadrupole Q2.
- 4.
- Emergency power supply shutdown for Electron HRS quadrupole Q3.
- 5.
- Emergency power supply shutdown for Electron HRS dipole.
- 6.
- Emergency power supply shutdown for Hadron HRS quadrupole Q1.
- 7.
- Emergency power supply shutdown for Hadron HRS quadrupole Q2.
- 8.
- Emergency power supply shutdown for Hadron HRS quadrupole Q3.
- 9.
- Emergency power supply shutdown for Hadron HRS dipole.
- 10.
- Emergency shut down of all ``clean" power in the end station - kills
clean power in both HRS shield house where the detector components are
located.
The keys have the following functions:
- 1.
- Disables power to all four Electron HRS superconducting magnet power
supplies. Essentially, this key electrically locks the four Electron HRS
crash buttons to their in (crash) positions. It
does not disable power to the cryogenic systems or magnet control
computer.
- 2.
- Disables power to all four Hadron HRS superconducting magnet power
supplies. Essentially, this key electrically locks the four Hadron HRS
crash buttons to their in (crash) positions. It
does not disable power to the cryogenic systems or magnet control
computer.
There are also TV cameras (displayed at the Hall A console) viewing the
HRS detectors, the general Hall area, the Hall A personnel access door, the
targets, and the beamline phosphor viewers.
Next: Independent Verification - Hall A
Up: Control of Equipment and
Previous: Control of Equipment and
10/13/1997