Small Angle GDH Target Meeting
August 15, 2002




    Patricia Solvignon reported on target analysis:
        Due to the large difference in lifetime measurements at UVa and JLab, the
    AFP loss correction to the lifetime measurement was studied.  Patricia used
    three methods to correct the lifetime:  multiple spin-down, correction point by
    point, and applying an equation provided by Alexandre Deur.  The three methods
    give comparable results, but the third tends to give slightly different lifetimes.

        For the ice cone cells, Steffen Jensen's method isn't valid for non-symmetric cells.
    Patricia used a lorentizian for the RTD's, which fits the data very well.

        Patricia presented the cell performance results for various cells tested in the past
    couple months

    Vincent Sulkosky discussed the target lab status:
        New equipment for the target system includes a computer, spectrum analyzer,
    and gaussmeter probe.  Modifications to the target system have been completed and
    tested with everything checking out fine.

        Calibration tests have been performed using the new ice cone cell design.  Water
    calibrations and Q-curve gains check out with the movement of the pick-up coils
    upstream.  Due to the cell geometry change, the flux code was changed to
    accommodate the changes.  Flux model tests with the new code are reasonable, but
    the collaboration would like more tests to check for geometry dependence.

        The new EPR coupler system works well after some modifications to the mounting
    design due to interferences in the reference cell position with the fiber.  One location
    will work for the spectrum analyzer in both longitudinal and transverse.

        NMR Results were reported on various cells tested recently.  Both NMR and EPR
    polarimetries agree to within about 2% for recent tests.

    Alexandre Deur gave an update on the cell status for E97-110:
        At UVa over a dozen cells have been made but there has only been three marginal
    cells and 2 good cells produced.  But one of the good cells Victor blew up.  At W&M
    no good ice cone cells produced, but tests are under way to understand why.  Reasons
    for the low success rate are the complicated cell design and how much the glass has
    been worked.  Cells that have had less work have had better lifetimes and polarization.

        Next week ice cone reference cells will be produced by both Mike and Willie.
    Alexandre wants to produce good c1720 standard cells with thinner walls.

    Todd Averett gave an update of the W&M target system:
        After filling two standard 40 cm cells this spring (Patrick and Harry), Todd found a
    vacuum leak, which explained their low lifetimes.  But since then two Ice cone cells
    have been filled with only ~ 3 hour lifetimes.  It is now believed that part of the problem
    is the glass blowers over worked the glass.  Todd has filled 4 spherical cells to test his
    system.  Initial results look promising.

    Jaideep Singh discussed the target lab status at UVa:
        UVa will continue to do cell lifetime and polarization measurements.  EPR system
    ready.  Plan to study AFP loss and EPR.  For cell characterization, the Ti-Sapph laser
    is being repaired.

        Jaideep looked into the cell lifetime difference between JLab and UVa.  Possible
    extra relaxation mechanism found at JLab with a rate of ~ 1/60 hours.  The extra rate
    agrees well with the lifetimes measured at JLab.
 

       Discussion on target moving/installation and other issues:
            For field direction, Alexandre Deur will check into how much a vertical
    angle effects physics for the experiment.  Documentation needed for the experiment
    includes:  Run Plan, COO, ESAD, OSP, RSAD.  Run sheets and shift checklist are
    also needed.  Tasks and coordination responsibilities were discussed.   Those that will
    be aiding during the installation and experiment should make sure their training is
    current.  Training includes:  RAD II, LOTO, Laser Safety, target operator, and
    compton.