Log entry time 03:16:34 on April21,2003
Entry number 97891
Followups:
keyword=target FSD problem
MCC was trying to deliver beam to Hall A. They had a problem with the target FSD. They asked to "cycle" the lifting motor. We moved the target from "Empty Target" to "BeO+C12" back to "Empty Target." This did not fix the problem. Later on MCC called back and said that one of the mechanical swtiches is not working properly. Therefore they will not be able to deliver beam until it is fixed. We don't know how to fix it, so we will wait.