continuing summary from entry 116905
15:00 MCC still having trouble sending good beam, sending tuned beam for tests - moved to 12C target just to be safe
15:48 update from MCC - problem is still related to fast feedback system. The checks they would run to look at this are similar to those from tonights scheduled system checks so the system checks have been moved to now. (In case this conflicts with the plan for cooling the septum tonight, blame MCC. They never called us to ask us about the new plan - moving tonight's system checks to now.)
MCC says "if beam is not back by 4:30, we are really screwing up."