keyword=Shift Summary
We started the shift with a vacuum problem in the north linac causing the beam studies to start early.
During the down time, a new reference cell was readied and right Q3 was made operational and Jack worked on the left Q3.
A quick check of the field shows the sign of the right Q3 is the same as it has always been (checked vs. a 2007 end of run file).