Run Coordinator's Report for Wednesday November 25 Day to Thursday
November 26 Owl
Summary
- 5 Owl shifts in the next week need a shift leader.
Please sign up!
- A great data taking day - we took 21 hours of ABU over the last 24
hours in which we achieved ~650 K good LD2 pairs for slug 8 and took 4
hours of aluminum asymmetry data.
Run Plan
- High current production running throughtout weekend.
Requests
- 5 Owl shifts in the next week need a shift leader. Please
sign up!
- Shift Leaders: please write a detailed shift summary (including
runs taken and any
activities) and submit the BTA for each shift. Please log CODA reboots
in the halog and shift summary.
- 3rd person: Please make sure to start and stop the HRS DAQ
at the same time as the parity DAQ and to do the prompt analysis and the
HRS analyzer for every run.
- 3rd person: please keep a careful eye on the online data display.
Most problems can be caught quickly this way.
- Please make sure that the shift checklist is done once each shift.
Data taken
- Production charge taken in the 24 hours ending Thursday Owl: 2.5
C (does not include aluminum asymmetry)
- Total production charge taken in all, end of Thursday Owl: 32.6