    User name brads

    Log entry time 18:35:39 on March 15, 2012

    Entry number 366582

    Followups:

    keyword=GEp/G2p status update -- Thursday

    We had significant problems getting beam steered into our Hall last night (Thursday OWL). ELOG 1699235 has a brief summary of the issues encountered. The big problem began around midnight and extended through to the morning. We are still not sure what the underlying problem is, but executed several diagnostic plans during a Controlled Access that ran through DAY shift. These include:
    1. Run a radiological survey of the beamline.
      1. Found some hot-spots on the line, notably at the septa exit flange. See Halog 366549, Halog 366552.
    2. Verify operation of the chicane magnets power supply
      1. Corrected the (minor) magnet cycling problem by lowering upper cycle current, and verified current at the magnet using clamp-on ammeter. ELOG 1699333
      2. Verified
    3. Verify chicane magnet fields
      1. Magnet group came to the Hall to take some direct field measurements of the FZ fields, but no report yet. Working on it...
    4. Relocate the Lumi ion chamber and add a new ion chamber to be above and below the dump entrance (ELOG 1699336). The hope is that this will give the Optics experts a better handle on the beam location in that region (where they are otherwise running blind).
    The other significant item addressed was an opportunistic replacement of the faulty control valve on the target buffer dewar (Halog 366548). The target group is wrapping this work up now.

    We will be locking the Hall as soon as the Target group is ready. Should be mid-SWING. Items in the queue once beam returns include (roughly in order of priority). A detailed runplan (as of this time) is attached to this Halog.

    1. BCM calorimeter run (Alex/Pengia)
    2. BPM/Harp runs (Alex/Pengia)
    3. TE measurement (if we can do this in parallel with 1, 2)
    4. Carbon, empty target dilution runs
    5. G2p production
    Note that we may drop or reorder as needed to make sure that we have time to polarize and start production running before midnight.

    Shift crew need to pay close attention to the following:



    A copy of this log entry has been emailed to: brads,g2p