User name Saha
Log entry time 09:44:33 on October 27,1998
Entry number 3822
Followups:
keyword=BCM Linearity test
Accelerator has started the test plan to do the Hall A BCM Linearity Test. They will first try to get as much beam to our hall (~ 35 microA). They then need to get settings to center the beam on the Faraday Cup 2 which will then be used to calibrate and stop beam to our hall. Hall B is now down. After they are ready, we will first ramp the current in 1 minute steps at 40, 20 10, 5, 2, 1, .5, .2 micrA. We will then do a step current calibration at the maximum current (5 cycles).