August 23rd 2024

From Hall A Wiki
Jump to: navigation, search
  • Updates
    • ECal
      • Timeline for installation
        • All PMTs installed this week
        • working on main cable trays from detector to bunker
        • next week main enclosure, can start cabling
        • cosmics by end of October
        • waiting for 39 FADCs end of October
        • Cosmics trigger : self trigger start to look at self trigger like NPS - Hanjie almost done with cosmics trigger firmware
        • ECAL students : Mahmoud VT, Kip UConn ( Simulation + hardware installation ), Jhih-ying (Fadc SCALER ...) UMass ( HCal )
        • need software for calibration and set VTP thresholds (Jhih-ying ?)
        • long cables from ESB last going in
        • cabling of FADC next week - will connect crate to network and TS when they are done
        • ECAL VTPs put together with SSP - no V1495 in final setup
    • HCAL
      • Jiwan and Ji Hing measured delay for VTP and analog - 2.5 uS for new firmware -
      • FADC scalers for HCal being implemented
      • Ben asked David Abbott to update to CODA run control for the sync reset so we can have digital trigger and GEM
      • sync reset enabled in DAQ now - might need to disable if GEM take data - might need to run HCAL , ECAL and GEM separately until CODA update
      • TS crate - but might get single DAQ -
      • HCAL TDC ? : reference time - V1495 output and analog - Trigger time from TS - could put trigger to look at efficiency
    • CDet
      • CDet moved in Hall A, all 6 modules, frame in 1 or 2 weeks, some things to move from Test Lab
      • Start taking cosmics with full detector readout
      • 1 months : cables needed to be made, 3 modules to be retroffited
      • HV : Lecroy crate in HRS - still need two negative HV to use as spare - maybe need 2 more to power the detector
      • CNU students : Jacob, May and Gabriel
      • software : plan to use high resolution software for VETROC
    • GEMs
      • arranged fibers on MPD crates
      • will work connecting to VTP and start low level
      • scintillator paddles for cosmics trigger : ~ estimated 1 week for flushing nitrogen + Ar 2nd week of September
      • ordered additionnal fibers
      • LV : could be turned on - using the SBS LV supply - New channels to be installed on break out
      • LV current : need to follow
      • test optical fiber
      • add firmware to MPD for monitoring
      • Histogramming method : ready to be studied - could be compiled for 32 MPDs
      • INFN VTP : check VXS key need to be tighen up
    • Beamline
      • to be recabled
      • will ask to Ciprian