December 20th 2024
From Hall A Wiki
- Updates
- Cdet
- All done with TDC ribbon cable this week
- LV still on going -
- working on software
- cosmics maybe 1 or 2 weeks next year
- all retroffiting done and installed
- HCal
- changed two PMTs - no more spare bases for one type - installed another one with base - can get signal when increasing HV ( 8 stages PMTs )
- Alex worked on standalone, almost done but issue with database -
- might switch VME readout for cosmics so can be added with all detectors
- cosmics trigger in ROC16 - In TS cosmics digital and analog
- Beamline
- All beamline crate reconnected
- helicity
- BCM cabling rearranged for scaler and helicity scaler
- helicity scalers and helicity decoding module installed and connected, working
- working on rol to include helicity decoding board - ready to test by early January - want to test LHRS and beamline
- not setup for xscaler and cable from NIM crates to be cabled - Bob and Jiwan will look on xscalers -
- want L1A for helicity scaler
- Ecal
- CODA config with all ECal crates
- Ben might be done with cosmics
- people still finishing cabling
- might still be a few channels and FADC to be fixed
- GEMs
- all HDMIs cable plugged
- 3 out 4 VTPs tested : clock phase issues on the 3 will be fixed - 2 MPDs might have issue with digital
- no cosmics planned
- 5th VTP crate up for histogramming test - I need 10gigE to finish setup
- Anu showed simulation - need to translate hits
- Cdet