Meeting 2021 03 03
From Hall A Wiki
GMn GEM commissioning Meetings: WEDNESDAY 10:00am - 11:00am
Link to all previous meetings: GMn GEM Commissioning Meeting
Contents
- 1 GEM setup for GEN-RP plans (Brad)
- 2 Update on INFN GEM commissioning (Evaristo, Roberto, Ezekiel, Holly)
- 3 Update on UVa GEM commissioning (Kondo & Anu)
- 4 TEDF BB UVa GEM data & MPD noise reduction (Xinzhan / Sean)
- 5 Update from cosmic data (Malinga & Thir)
- 6 Update on the Tracking efficiency / resolution (Andrew)
- 7 Update on the High rate DAQ development (Ben, Alex, Paolo, Holly, Sean)
GEM setup for GEN-RP plans (Brad)
Update on INFN GEM commissioning (Evaristo, Roberto, Ezekiel, Holly)
Update on UVa GEM commissioning (Kondo & Anu)
- From Brad's email:
- Walt Akers has confirmed that the largest GEM frame can be moved to the EEL/124 cleanroom as soon as it's ready. (The two smaller frames stay in the ESB as planned).
- The base alignment spacers (large frame) we were given from Hall A are not the correct height. Check with Chris the designer if can correct this (Status?).