Near term work plan (all)
- Installation of HV dividers on BB: April 18 for 3 weeks (3d/layer + 3 float days).
- BB APV status
- 10 APVs with missing strips.
- ~400 strips missing total (out of 30,720)
- Only 2 APVs near the center of the acceptance, about 60 strips.
- Need 1 layer with HV divider upgrade for the SBS stack.
- HV divider upgrade for INFN GEMs
- Brad: update on date for install of SBS GEMs in Hall A.
- Need 2-3 months for APVs for 10th SBS layer.
- Need 1 week to install all dividers on BB GEMs and test.
Update on BB GEMs(Sean, Ezekiel, Holly, Anu)
- Negative tracking results - Sean
- Full plots in the HALOG, https://logbooks.jlab.org/entry/3986717
Update on UVa GEM layers for GEn-RP (Anu, John, Thir)
- EEL 125 GEM DAQ updates -- will present next week
Update on INFN GEM layers for GEn-RP (Ezekiel, Holly, Evaristo)
DAQ updates (Ben, Bryan, Alex)
- schematic of setup?
- FIR filter?
- Update on: need 2 DC working in Hall A