GMn GEM commissioning Meetings: WEDNESDAY 10:30am - 11:30am
Link to all previous meetings: GMn GEM Commissioning Meeting
Please use sbs_gems mailing list for plots/communications and HALOG entries relevant to GEMs!
Contents
Near term work plan
- See installation plan for SBS here: plan
- Installation of HV dividers on BB: work plan
- Thoughts on special run requests during GEn:
- Luminosity studies (Nilanga)
- Full readout studies for negative pulse studies and etc (Sean)
Update on INFN GEM layers for GEn-RP
- 0.5" spacers arrived, working on INFN install plan for EEL.
Update on UVa GEM layers for GEn-RP
Update on BB GEMs
- All GEMs back in BB.
- One APV giving trouble, currently investigating.
- Taking new pedestals and switching over to Ar/CO2 in the next few weeks.
Common Mode Algorithms
- Currently testing different ideas for use in GEn.
- Results coming within a week
DAQ updates (Ben, Bryan, Alex)
- schematic of setup?
- FIR filter?
- Update on: need 2 DC working in Hall A