Meeting 2022 05 25
From Hall A Wiki
GMn GEM commissioning Meetings: WEDNESDAY 10:30am - 11:30am
Link to all previous meetings: GMn GEM Commissioning Meeting
Please use sbs_gems mailing list for plots/communications and HALOG entries relevant to GEMs!
Contents
Near term work plan
- See installation plan for SBS here: plan
- Installation of HV dividers on BB: work plan
- Thoughts on special run requests during GEn:
- Luminosity studies (Nilanga)
- Full readout studies for negative pulse studies and etc (Sean)
Update on INFN GEM layers for GEn-RP
- Layers assembled and ready to be inserted in inline stack. Plan to run up HV this week.
Update on UVa GEM layers for GEn-RP
Update on BB GEMs
- All APVs plugged in and working.
- Will perform a pedestal analysis soon.
- Waiting for HiVolta supply to evaluate pedestals on layer 0.
Common Mode Algorithms
- CM negative bias corrections in SBS-offline
- CM algorithm comparisons for online subtraction
- Event displays
DAQ updates (Ben, Bryan, Alex)
- schematic of setup?
- FIR filter?
- Update on: need 2 DC working in Hall A