Meeting 2023 01 24
From Hall A Wiki
GMn GEM commissioning Meetings: WEDNESDAY 10:30am - 11:30am
Link to all previous meetings: GMn GEM Commissioning Meeting
Please use sbs_gems mailing list for plots/communications and HALOG entries relevant to GEMs!
GEM inventory for GEn-RP and GEp:
Work plan for GEn-RP
- Testing RP layers in the Hall
- Remove the SBS GEM stack around Jan 25 for HV upgrades and APV repairs/swaps.
- Work on SBS GEM is 15 days until Feb 15.
- We plan to swap modules to put the HV inputs on the same side
- Build the SBS GEM bunker after the SBS and HCAL moved into position.
- Joe B ordered some new GEM LV breakout boxes. We will continue to use the electronics/LV in place while we upgrade and troubleshoot.
- Holly, Vimukthi coordinating with Joe
- Second supply arrived if needed.