GMn GEM commissioning Meetings: WEDNESDAY 10:30am - 11:30am
Link to all previous meetings: GMn GEM Commissioning Meeting
Please use sbs_gems mailing list for plots/communications and HALOG entries relevant to GEMs!
GEM inventory for GEn-RP and GEp:
Work plan for GEn-RP
- Inline GEM layers and RP layers work is complete. Probably to be installed on SBS platform early next week.
- Update on preparations for XW layer.
- Some setup of the HV electronics on the network and routing of patch + cables. Still work to be done.
- Once the GEMs back on SBS, we should begin running the HDMI cables.
- Will need help moving the GEMs in EEL 125 for Hall B.
- Joe B thinks LV system could be ready by 1 March (in progress)
DAQ updates (Ben, Bryan, Alex)
- https://redmine.jlab.org/projects/sbs-daq-gen-rp-gems/issues
- all HV crates on Hall A network
- Do we need more reboot switch for HV ?