GMn GEM commissioning Meetings: WEDNESDAY 10:30am - 11:30am

Link to all previous meetings: GMn GEM Commissioning Meeting

Please use sbs_gems mailing list for plots/communications and HALOG entries relevant to GEMs!


Progress from this past week

  • Completed cabling the GEMs on the platform and low level test [1]
  • Discussion of shielding for GEM hut
  • Pedestal data taking on Monday
    • some APVs have to be commented out as they could not be configured
    • 2 MPDs could not be found
    • sbsvtp4 is likely missing 10gigE fiber

Plan for the next few days

  • Put in the fiber on sbsvtp4
  • fix the remaining APV and MPDs issues
  • Increases gas flow to GEMs. The GEMs are getting ArCO2 since last Thursday, but at a reduced flow rate.
  • Check HV connections. The layer 15 is missing a few HV cables, they are too high and out of reach.


Setting up cosmic readout

  • Clean up cables
  • Set up DAQ computer (we will use adaq1)
  • Set up the third VTP crate (mostly done)
  • Rearrange fibers, HV and NIM cables.
  • Set up the scintillators and form the trigger
  • Connect the GEM to LV
  • Set up the MPDs (connecting the HDMIs to MPDs)
  • Begin low level test (find and replace any problematic APV, mpd, etc) (the front tracker is being tested)
  • Begin HV conditioning on N2
  • Switch over to ArCO2

GEp preparations

  • Our GEM task list is here: workplan
  • Remove layers, isolate shorted sectors, repair APVs as needed
  • Joe B will add LV inputs for new GEMs in the stack, we will need to make those cables (4 more layers)
  • Install BB gas distribution from SBS line -- DSG will do this (completed)
  • Further calibrations of SBS gas mix
  • Repair/troubleshoot problematic CAEN crates -- DSG working on this
  • MPD testing and repair
  • Prepare and install pixel layers (long term)

Suggested order of work

  • Move layers into front and back tracker (done)
  • Upgrade the BB XY layer to SHV (done)
  • Fabricate remaining LV cables
  • Repair/replace L6 modules, install as last layer in Back Tracker, until EEL layer is ready (work in progress)
  • For cosmics, bring bars (HV+signal cables) to table and make a readout trigger. Work with techs to bring out 1 layer at a time?
  • For cosmics, move stack to be near RHRS, we can access all gas lines, setup readout, LV etc. (completed)
    • Move BB crates to SBS rack (completed)
    • Setup scintillators around the stack and run for a longer period. (work in progress)
  • Other work, setup gas flow in EEL to chamber. Finish HV upgrade & test. (work in progress)

DAQ updates (Ben, Bryan, Alex)

  • Implement and test histogram method


https://redmine.jlab.org/projects/sbs-daq-gep-gems/issues