- General considerations
- Kijun Park is the current Run Coordinator. Please contact directly via RC phone 757-876-1787
- Follow the generic Instructions for shift takers
- Shift leaders: Please make sure to fill out the beam time accounting form and write a "Shift Summary" log entry at the end of your shift regardless if there is beam or not.
- In general, Hall technical staff should not be contacted by the shift crew - please call the RC first.
- The target operator is required to supervise the cryo-target.
- Make sure to use the DVCS CODA configuration for all runs (even when taking single arm HRS data).
- Instructions for this shift
- 0) Check the beam position
- - request beam position: BPM A=(+1.5:0.75), BPM D=(+1.5:-0.75) ---- please double check
- 1) When beam arrives to the Hall
- - Ask MCC to run the Harps: 1H04A/B (close to target)
- - halog the results
- 2) Confirm the beam position using the carbon hole target.
- - request CW 5uA without raster
- - check the scaler rate rastered target up to 2x2 or 3x3
- take LHRS & RHRS run with prescale PS1=1
- 3) Do SpotL and SpotR
- - to check the hole is centered on the raster current X vs. Y plot
- 4) Bullseye scan
- - once beam is centered
- - scan with both LHRS & RHRS
- - PS1=1, PS8=10 : for RHRS
- - 103kHz = 4096, S0&S2m =1 : for LHRS
- 0) Check the beam position
Optics Calibration Data