Difference between revisions of "G2p Safety Readiness Review"

From Hall A Wiki
Jump to: navigation, search
(Draft and Supporting Documents)
(Draft and Supporting Documents)
Line 97: Line 97:
 
   ! link
 
   ! link
 
|-
 
|-
   | FZ #2 Magnet, Magnet Arms, and Girder Adjustments For g2P Experiment  (draft/in review)
+
   | FZ #2 Magnet, Magnet Arms, and Girder Adjustments For g2P Experiment  (submitted/in review)
 
   | [http://hallaweb.jlab.org/experiment/g2p/meetings/safety_011712/docs/draft/OSPforFZ2adjustmenttask-rev1-30-12.doc OSP]
 
   | [http://hallaweb.jlab.org/experiment/g2p/meetings/safety_011712/docs/draft/OSPforFZ2adjustmenttask-rev1-30-12.doc OSP]
 
|-
 
|-
   | Polarized Target OSP (draft/in review)
+
   | Polarized Target OSP (submitted/in review)
 
   | [http://hallaweb.jlab.org/experiment/g2p/meetings/safety_011712/docs/draft/OSP_g2pTarget.docx OSP]  
 
   | [http://hallaweb.jlab.org/experiment/g2p/meetings/safety_011712/docs/draft/OSP_g2pTarget.docx OSP]  
 +
|-
 +
  | 3rd Arm Access THA
 +
  | [http://hallaweb.jlab.org/experiment/g2p/meetings/safety_011712/docs/draft/G2P3rd_arm_access_THA.doc doc]  (submitted/in review)
 +
|-
 +
  | 3rd Arm Access
 +
  | [http://hallaweb.jlab.org/experiment/g2p/meetings/safety_011712/docs/draft/G2P_3dr_arm_access.doc doc]  (submitted/in review)
 
|-
 
|-
 
   | Conduct of Operations (COO)
 
   | Conduct of Operations (COO)
Line 117: Line 123:
 
   | Pre Beam Checklist  
 
   | Pre Beam Checklist  
 
   | [http://hallaweb.jlab.org/experiment/g2p/meetings/safety_011712/docs/draft/G2P_pre_beam_checkist_9-21-11.docx docx]
 
   | [http://hallaweb.jlab.org/experiment/g2p/meetings/safety_011712/docs/draft/G2P_pre_beam_checkist_9-21-11.docx docx]
|-
 
  | 3rd Arm Access THA
 
  | [http://hallaweb.jlab.org/experiment/g2p/meetings/safety_011712/docs/draft/G2P3rd_arm_access_THA.doc doc]
 
|-
 
  | 3rd Arm Access
 
  | [http://hallaweb.jlab.org/experiment/g2p/meetings/safety_011712/docs/draft/G2P_3dr_arm_access.doc doc]
 
 
|-
 
|-
 
   | Local Dump
 
   | Local Dump

Revision as of 15:44, 3 February 2012

Overview

On January 17, JLab will review the readiness of E08-027/007 to safely begin production data taking. This wikipage is the central repository of all collaboration information relevant to this review. The official charge is here. In addition, the committee has also asked us to address these specific questions.


Comments/Suggestions from the committee are posted here

Draft Response here (last update 2/2/2012)

Specific response from B. Dillon-Townes here

Review Agenda

January 17, 2012; JLab F225, 1:00-5:00 pm

Time Topic Presenter
1:00 - 1:20 Introduction/Overview J. P. Chen
1:20 - 1:40 Polarized Target update (short-note) C. Keith
1:40 - 2:00 g2p/GEp Beamline T. Michalski
2:00 - 2:20 Beamline runorbits Y. Roblin
2:20 - 3:00 Break
3:00 - 3:20 Engineering, Design & Field Mapping R. Wines
3:20 - 3:40 Hall A Installation, Mechanical Structures E. Folts
3:40 - 4:00 Radiation Control P. Degtiarenko
4:00 - 4:20 Radiation Damage (updated 1/27/2012) Dose Rates from Local Dump G. Kharashvili
4:20 - 4:40 Experiment Preparation K. Slifer
4:40 - 5:00 Discussion

Finalized Documents

Title link
Procedure for Maintenance and Operation of Hall A FZ Magnets and FZ Power Supplies OSP
Safe Operation of the Big Bite Power Supply OSP
Safe Operation of the HKS Power Supply OSP
Septum Magnet Commissioning, Operation, and Troubleshooting OSP
Hall A Slow Raster OSP
Hall A Tungsten Calorimeter Operation OSP


Draft and Supporting Documents

Title link
FZ #2 Magnet, Magnet Arms, and Girder Adjustments For g2P Experiment (submitted/in review) OSP
Polarized Target OSP (submitted/in review) OSP
3rd Arm Access THA doc (submitted/in review)
3rd Arm Access doc (submitted/in review)
Conduct of Operations (COO) pdf
Experimental Safety Assesment Document (ESAD) pdf
Polarized Target Primer pdf
Hazard Awareness & Safety Guidelines pdf pdf
Pre Beam Checklist docx
Local Dump coversheet doc
December Commissioning TOSP
Septa Field Mapping TOSP

Notes