| ==Overview== | | ==Overview== |
− | On January 17, JLab will review the readiness of E08-027/007 to safely begin production data taking. This wikipage is the central repository of all collaboration information relevant to this review. The official charge is [http://hallaweb.jlab.org/experiment/g2p/meetings/safety_011712/charge/review_charge_g2p-GEp_2011_20111017.doc here]. In addition, the committee has also asked us to address [http://hallaweb.jlab.org/experiment/g2p/meetings/safety_011712/charge/questions.txt these specific questions]. | + | On January 17, JLab reviewed the readiness of E08-027/007 to safely begin production data taking. This wikipage is the central repository of all collaboration information relevant to this review. The official charge is [http://hallaweb.jlab.org/experiment/g2p/meetings/safety_011712/charge/review_charge_g2p-GEp_2011_20111017.doc here]. In addition, the committee asked us to address [http://hallaweb.jlab.org/experiment/g2p/meetings/safety_011712/charge/questions.txt these specific questions]. |
| | | |
| | | |
− | Comments/Suggestions from the committee are posted [http://hallaweb.jlab.org/experiment/g2p/meetings/safety_011712/charge/committee_comments.txt here]
| + | The review comments and the collaboration response are [http://hallaweb.jlab.org/experiment/g2p/meetings/safety_011712/charge/committee_comments.pdf here] |
− | | + | *(updated 2/8/2012: Interlock schematic). |
− | Draft Response [http://hallaweb.jlab.org/experiment/g2p/meetings/safety_011712/charge/committee_comments.pdf here] (last update 2/2/2012)
| + | *(updated 2/10/2012: Radiation damage to Septa epoxy). |
| | | |
| ==Review Agenda == | | ==Review Agenda == |
Line 61: |
Line 61: |
| |} | | |} |
| | | |
− | ==Finalized Documents==
| |
| | | |
− | {|border=0
| |
− | |-bgcolor=Grey
| |
− | ! Title
| |
− | ! link
| |
− | |-
| |
− | | Procedure for Maintenance and Operation of Hall A FZ Magnets and FZ Power Supplies
| |
− | | [http://hallaweb.jlab.org/experiment/g2p/meetings/safety_011712/docs/final/ENG-11-035-OSP.pdf OSP]
| |
− | |-
| |
− | | Safe Operation of the Big Bite Power Supply
| |
− | | [http://hallaweb.jlab.org/experiment/g2p/meetings/safety_011712/docs/final/OSP__BigBite_Power_Supply.pdf OSP]
| |
− | |-
| |
− | | Safe Operation of the HKS Power Supply
| |
− | | [http://hallaweb.jlab.org/experiment/g2p/meetings/safety_011712/docs/final/OSP__HKS_Power_Supply.pdf OSP]
| |
− | |-
| |
− | | Septum Magnet Commissioning, Operation, and Troubleshooting
| |
− | | [http://hallaweb.jlab.org/experiment/g2p/meetings/safety_011712/docs/final/OSP__Septum_Commssioning_Operation.pdf OSP]
| |
− | |-
| |
− | | Hall A Slow Raster
| |
− | | [http://hallaweb.jlab.org/experiment/g2p/meetings/safety_011712/docs/final/PHY-11-046-OSP.pdf OSP]
| |
− | |-
| |
− | | Hall A Tungsten Calorimeter Operation
| |
− | | [http://hallaweb.jlab.org/experiment/g2p/meetings/safety_011712/docs/final/PHY-11-047-OSP.pdf OSP]
| |
− | |}
| |
− |
| |
− |
| |
− | ==Draft and Supporting Documents==
| |
− |
| |
− | {|border=0
| |
− | |-bgcolor=Grey
| |
− | ! Title
| |
− | ! link
| |
− | |-
| |
− | | Polarized Target OSP (draft/in review)
| |
− | | [http://hallaweb.jlab.org/experiment/g2p/meetings/safety_011712/docs/draft/OSP_g2pTarget.docx OSP]
| |
− | |-
| |
− | | Conduct of Operations (COO)
| |
− | | [http://hallaweb.jlab.org/experiment/g2p/meetings/safety_011712/docs/draft/coo_standard.pdf pdf]
| |
− | |-
| |
− | | Experimental Safety Assesment Document (ESAD)
| |
− | | [http://hallaweb.jlab.org/experiment/g2p/meetings/safety_011712/docs/draft/esad.pdf pdf]
| |
− | |-
| |
− | | Polarized Target Primer
| |
− | | [http://hallaweb.jlab.org/experiment/g2p/meetings/safety_011712/docs/draft/g2p_target_primer.pdf pdf]
| |
− | |-
| |
− | | Hazard Awareness & Safety Guidelines
| |
− | | [http://hallaweb.jlab.org/experiment/g2p/meetings/safety_011712/docs/draft/Hazard_Awareness.pdf pdf] [http://hallaweb.jlab.org/experiment/g2p/meetings/safety_011712/docs/draft/safety_guidelines.pdf pdf]
| |
− | |-
| |
− | | Pre Beam Checklist
| |
− | | [http://hallaweb.jlab.org/experiment/g2p/meetings/safety_011712/docs/draft/G2P_pre_beam_checkist_9-21-11.docx docx]
| |
− | |-
| |
− | | 3rd Arm Access THA
| |
− | | [http://hallaweb.jlab.org/experiment/g2p/meetings/safety_011712/docs/draft/G2P3rd_arm_access_THA.doc doc]
| |
− | |-
| |
− | | 3rd Arm Access
| |
− | | [http://hallaweb.jlab.org/experiment/g2p/meetings/safety_011712/docs/draft/G2P_3dr_arm_access.doc doc]
| |
− | |-
| |
− | | Local Dump
| |
− | | [http://hallaweb.jlab.org/experiment/g2p/meetings/safety_011712/docs/draft/G2P_dump_OSP_cover_sheet.doc coversheet] [http://hallaweb.jlab.org/experiment/g2p/meetings/safety_011712/docs/draft/G2P_dump_THA.doc doc]
| |
− | |-
| |
− | | December Commissioning
| |
− | | [http://hallaweb.jlab.org/experiment/g2p/meetings/safety_011712/docs/final/PHY-11-034-TOSP.pdf TOSP]
| |
− | |-
| |
− | | Septa Field Mapping
| |
− | | [http://hallaweb.jlab.org/experiment/g2p/meetings/safety_011712/docs/final/PHY-11-035-TOSP.pdf TOSP]
| |
− | |}
| |
| | | |
− | ==Notes==
| + | All Safety Documentation is [https://hallaweb.jlab.org/wiki/index.php/G2p_documentation here] |
− | *Overview of JLab's [http://wwwold.jlab.org/ehs//ehsmanual/3310.htm Operational Safety Procedure Program].
| + | |
− | *JLab [http://wwwold.jlab.org/ehs/ehsmanual/3310T2.htm OSP template].
| + | |
− | *List of previous JLab [https://jlabdoc.jlab.org/docushare/dsweb/View/Collection-1918 OSPs].
| + | |
− | *JLab [https://jlabdoc.jlab.org/docushare/dsweb/ApplySimpleSearch Docushare]
| + | |
On January 17, JLab reviewed the readiness of E08-027/007 to safely begin production data taking. This wikipage is the central repository of all collaboration information relevant to this review. The official charge is here. In addition, the committee asked us to address these specific questions.