Difference between revisions of "Thursday, February 27, 2014 2:30pm EST - Compton"
From Hall A Wiki
(→Minutes) |
(→Minutes) |
||
Line 27: | Line 27: | ||
### Chuck Long (spectrometer group - Jack Segal running) | ### Chuck Long (spectrometer group - Jack Segal running) | ||
### single-pass frequency doubling only problem (expertise at the lab) | ### single-pass frequency doubling only problem (expertise at the lab) | ||
− | #### still trying to locate parts - crystal | + | #### still trying to locate parts - crystal (several purchased) |
#### thermoelectric chillers to control temp | #### thermoelectric chillers to control temp | ||
#### stage still on table | #### stage still on table |
Revision as of 15:46, 27 February 2014
Previous meeting: Tuesday, December 10, 2013 11am EST - Compton
Tentative Agenda
- Updates
- laser (Kent)
- DAQ (Bob/Alex)
- photon detector (Greg/Vahe)
- electron detector (Juliette/Dipangkar)
- magnetic field mapping (Kent)
- beamline status/accelerator schedule (Alex)
- consequences of restructuring (Dave/Thia)
- Next meeting time
Minutes
Attending: Juliette, Dustin, Dave, Alex, Brian, Greg, Kent
- Updates - Near term and long term goals, mostly near term (DVCS, PREX/CREX)
- laser (Kent and Dave)
- near term - getting running again (how it was set up before)
- few kW green power (easier then IR)
- green good for PREX
- work in hall (not in laser lab - 2nd floor ARC)
- Chuck Long (spectrometer group - Jack Segal running)
- single-pass frequency doubling only problem (expertise at the lab)
- still trying to locate parts - crystal (several purchased)
- thermoelectric chillers to control temp
- stage still on table
- Abdurahim - thesis - photos, etc.
- trying to organize after restructuring
-
- High flip rate capability of the DAQ (MOLLER)
-
- DVCS in the fall
- Synchrotron light at 12 GeV running
- laser (Kent and Dave)