Tuesday, December 10, 2013 11am EST - Compton
From Hall A Wiki
Previous meeting: Thursday, November 14, 2013 2pm EST - Compton
Tentative Agenda
- Updates
- Next meeting time
Minutes
Attending: Juliette, Ryan, Vahe, Brian, Greg, Dustin, Alex, Sirish
- Ryan - simulation up and running
- Alex - working with detector
- Sirish - project timeline - readines review
- beam expected middle of March
- physics in September/October next year
- electron detector mechanics and integration mostly done
- photon detector needs to be raised
- support stand needs to be jacked up
- section of beamline for photon needs work - Joyce Miller could help
- photon detector needs to be refurbished - at JLAB?
- needs to be surveyed to see if it can be removed from the hall - work with Joyce remotely?
- it would have to be dismounted and moved to a lower background area
- metal cutting at CMU - could junk the small tubes if radioactive
- finger scintillators 1/4", tubes quite a bit bigger
- mid-February at latest to get back in the hall
- field measurements
- integral Bdl measurement - wire measurement (goes into beam tune)
- Kent did 3D measurement of fringe fields that goes in to electron analysis, reported at Hall A meeting
- lead tungstate for higher energy running - GSO not ideal for higher energies
- high rate counting mode for DAQ - GSO has longer pulse than lead tungstate
- cost effective
- lead tungstate contains the whole shower (needs to be 60-70 mm in diameter)
- next meeting - week of the 20th (send a Doodle poll the week of the 13th)
Return to Compton