(New page: Previous meeting: Tuesday, December 10, 2013 11am EST - Compton == Tentative Agenda == # Updates # Next meeting time <br> == Minutes == Attending: Juliette, Ryan, Vahe, Brian, Gre...)
 
(Minutes)
 
(14 intermediate revisions by the same user not shown)
Line 4: Line 4:
  
 
# Updates
 
# Updates
 +
## laser (Kent)
 +
## DAQ (Bob/Alex)
 +
## photon detector (Greg/Vahe)
 +
## electron detector (Juliette/Dipangkar)
 +
## magnetic field mapping (Kent)
 +
## beamline status/accelerator schedule (Alex)
 +
# consequences of restructuring (Dave/Thia)
 
# Next meeting time
 
# Next meeting time
  
Line 10: Line 17:
 
== Minutes ==
 
== Minutes ==
  
Attending: Juliette, Ryan, Vahe, Brian, Greg, Dustin, Alex, Sirish
+
Attending: Juliette, Dustin, Dave, Alex, Brian, Greg, Kent
  
# Ryan - simulation up and running
+
# Updates - Near term and long term goals, mostly near term (DVCS, PREX/CREX)
# Alex - working with detector
+
## laser (Kent/Dave)
# Sirish - project timeline - readines review
+
###  near term - getting running again (how it was set up before)
## beam expected middle of March
+
### few kW green power (easier then IR)
## physics in September/October next year
+
### green good for PREX
## electron detector mechanics and integration mostly done
+
### work in hall (not in laser lab - 2nd floor ARC)
## photon detector needs to be raised
+
### Chuck Long (spectrometer group - Jack Segal running)
### support stand needs to be jacked up
+
### single-pass frequency doubling only problem (expertise at the lab)
### section of beamline for photon needs work - Joyce Miller could help
+
#### still trying to locate parts - crystal (several purchased)
## photon detector needs to be refurbished - at JLAB?
+
#### thermoelectric chillers to control temp
### needs to be surveyed to see if it can be removed from the hall - work with Joyce remotely?  
+
#### stage still on table
### it would have to be dismounted and moved to a lower background area
+
#### Abdurahim - thesis - photos, etc.
### metal cutting at CMU - could junk the small tubes if radioactive
+
### trying to organize after restructuring
### finger scintillators 1/4", tubes quite a bit bigger
+
### Just photon okay for DVCS (don't want to break anything :))
### mid-February at latest to get back in the hall
+
### actuators for optics (after laser is running)
# field measurements
+
### with 12 GeV, green won't fit in beampipe at 12 GeV - redesign e- det can
## integral Bdl measurement - wire measurement (goes into beam tune)
+
### small slot - French connection? - redesigned?
## Kent did 3D measurement of fringe fields that goes in to electron analysis, reported at Hall A meeting
+
### last real-world experience - power 5kW? - mirrors degrade in tunnel
# lead tungstate for higher energy running - GSO not ideal for higher energies
+
## DAQ (Bob/Alex)
## high rate counting mode for DAQ - GSO has longer pulse than lead tungstate
+
### put computer back in counting house
## cost effective
+
### trying to run the flash ADC DAQ on it
## lead tungstate contains the whole shower (needs to be 60-70 mm in diameter)
+
### High flip rate capability of the DAQ (MOLLER)
# next meeting - week of the 20th (send a Doodle poll the week of the 13th)
+
#### old DAQ - ran at 30 Hz
 +
#### trigger supervisor, event triggered DAQ
 +
#### PREX won't use e- det - flash ADC with photon det
 +
## photon detector (Greg/Brian)
 +
### existing GSO brought back to CMU
 +
#### modified so it will fit
 +
#### more adjustability - need some safety stops on xy table
 +
#### eventual plan - two detectors one for higher energy
 +
### analyzing power factor of 2 with green laser
 +
### with GSO photon energy is not as much of a factor
 +
### photon used for DVCS
 +
### looking at PbW for 12 GeV
 +
#### no timeline
 +
#### Sirish had a source for large crystal - Shanghai?
 +
#### 2cm square are common - wrap them together... if no choice
 +
#### 3% would be pretty useful for DVCS
 +
#### Hall C four crystals will fit (but not the box they're in)
 +
### cooling PbW
 +
#### light output fluctuates near room temp.
 +
#### more light with cooler -  15 C?
 +
#### need to calibrate with spectrum in counting, and would be distorted
 +
#### if energy changes, then effects from that, too
 +
### radiation level too high for lead glass? (1 MHz photon rate)
 +
### better for lead flouride (3x3cmsq, 18.6 cm long?)
 +
### for near term - 4 crystal lead tunsgate in DVCS with and without cooling
 +
## electron detector (Juliette/Alex)
 +
### MOU completed
 +
### Alex preparing contract to loan
 +
#### single plane w/half not functional
 +
#### French A/D
 +
#### QWAD
 +
### plan to try to get a postdoc for Compton/PREX
 +
### student here to start with borrowed setup, building lab
 +
## magnetic field mapping (Kent)
 +
### quantitative disagreement with TOSCA
 +
### inside the dipole, 30-40 cm 10^-3 differences
 +
### nobody ever mapped it - Alex may have it?
 +
### Bdl was measured...
 +
## beamline status/accelerator schedule (Alex)  
 +
### upcoming beam test in March
 +
### DVCS in the fall
 +
### 12 GeV halo bigger
 +
### Synchrotron light at 12 GeV running
 +
# consequences of restructuring
 +
## Halls A/C merged
 +
## Dave is tasked with Hall A Compton
 +
## plan to make the systems more similar
 +
### DAQ more like Hall A
 +
### laser more like Hall A (fiber amp., narrow line width IR)
 +
## manpower - same amount of work done by less people
 +
### user support will be very valuable
 +
### photon detector under control
 +
### electron detector has challenges, but people are working on it
 +
# next meeting time
 +
## keep meeting with a large group
 +
## once a month for now, more frequent in summer
 +
## beginning of April - Doodle poll last week of March
  
 
<br><br> Return to [[Compton]]
 
<br><br> Return to [[Compton]]

Latest revision as of 16:53, 27 February 2014

Previous meeting: Tuesday, December 10, 2013 11am EST - Compton

Tentative Agenda

  1. Updates
    1. laser (Kent)
    2. DAQ (Bob/Alex)
    3. photon detector (Greg/Vahe)
    4. electron detector (Juliette/Dipangkar)
    5. magnetic field mapping (Kent)
    6. beamline status/accelerator schedule (Alex)
  2. consequences of restructuring (Dave/Thia)
  3. Next meeting time


Minutes

Attending: Juliette, Dustin, Dave, Alex, Brian, Greg, Kent

  1. Updates - Near term and long term goals, mostly near term (DVCS, PREX/CREX)
    1. laser (Kent/Dave)
      1. near term - getting running again (how it was set up before)
      2. few kW green power (easier then IR)
      3. green good for PREX
      4. work in hall (not in laser lab - 2nd floor ARC)
      5. Chuck Long (spectrometer group - Jack Segal running)
      6. single-pass frequency doubling only problem (expertise at the lab)
        1. still trying to locate parts - crystal (several purchased)
        2. thermoelectric chillers to control temp
        3. stage still on table
        4. Abdurahim - thesis - photos, etc.
      7. trying to organize after restructuring
      8. Just photon okay for DVCS (don't want to break anything :))
      9. actuators for optics (after laser is running)
      10. with 12 GeV, green won't fit in beampipe at 12 GeV - redesign e- det can
      11. small slot - French connection? - redesigned?
      12. last real-world experience - power 5kW? - mirrors degrade in tunnel
    2. DAQ (Bob/Alex)
      1. put computer back in counting house
      2. trying to run the flash ADC DAQ on it
      3. High flip rate capability of the DAQ (MOLLER)
        1. old DAQ - ran at 30 Hz
        2. trigger supervisor, event triggered DAQ
        3. PREX won't use e- det - flash ADC with photon det
    3. photon detector (Greg/Brian)
      1. existing GSO brought back to CMU
        1. modified so it will fit
        2. more adjustability - need some safety stops on xy table
        3. eventual plan - two detectors one for higher energy
      2. analyzing power factor of 2 with green laser
      3. with GSO photon energy is not as much of a factor
      4. photon used for DVCS
      5. looking at PbW for 12 GeV
        1. no timeline
        2. Sirish had a source for large crystal - Shanghai?
        3. 2cm square are common - wrap them together... if no choice
        4. 3% would be pretty useful for DVCS
        5. Hall C four crystals will fit (but not the box they're in)
      6. cooling PbW
        1. light output fluctuates near room temp.
        2. more light with cooler - 15 C?
        3. need to calibrate with spectrum in counting, and would be distorted
        4. if energy changes, then effects from that, too
      7. radiation level too high for lead glass? (1 MHz photon rate)
      8. better for lead flouride (3x3cmsq, 18.6 cm long?)
      9. for near term - 4 crystal lead tunsgate in DVCS with and without cooling
    4. electron detector (Juliette/Alex)
      1. MOU completed
      2. Alex preparing contract to loan
        1. single plane w/half not functional
        2. French A/D
        3. QWAD
      3. plan to try to get a postdoc for Compton/PREX
      4. student here to start with borrowed setup, building lab
    5. magnetic field mapping (Kent)
      1. quantitative disagreement with TOSCA
      2. inside the dipole, 30-40 cm 10^-3 differences
      3. nobody ever mapped it - Alex may have it?
      4. Bdl was measured...
    6. beamline status/accelerator schedule (Alex)
      1. upcoming beam test in March
      2. DVCS in the fall
      3. 12 GeV halo bigger
      4. Synchrotron light at 12 GeV running
  2. consequences of restructuring
    1. Halls A/C merged
    2. Dave is tasked with Hall A Compton
    3. plan to make the systems more similar
      1. DAQ more like Hall A
      2. laser more like Hall A (fiber amp., narrow line width IR)
    4. manpower - same amount of work done by less people
      1. user support will be very valuable
      2. photon detector under control
      3. electron detector has challenges, but people are working on it
  3. next meeting time
    1. keep meeting with a large group
    2. once a month for now, more frequent in summer
    3. beginning of April - Doodle poll last week of March



Return to Compton