Difference between revisions of "Commissioning Run Plan"
From Hall A Wiki
(→Pre-beam Checklist) |
(→Pre-beam Checklist) |
||
Line 7: | Line 7: | ||
== Pre-beam Checklist == | == Pre-beam Checklist == | ||
<b>Trigger Checkout</b> (Experts) | <b>Trigger Checkout</b> (Experts) | ||
− | Checkout trigger timing | + | * Checkout trigger timing |
− | Checkout of EDTM (Barak Schmookler) | + | * Checkout of EDTM (Barak Schmookler) |
− | Think about adding 60, 100, 150, and 200 ns wide electronic deadtime scalers | + | * Think about adding 60, 100, 150, and 200 ns wide electronic deadtime scalers |
* This has been found to be a robust method for determining electronic deadtime in Hall C and we | * This has been found to be a robust method for determining electronic deadtime in Hall C and we |
Revision as of 15:42, 6 October 2014
For the Fall of 2014 assume:
- max 20 uA but for short times it can go higher for boiling studies and BCM calibration.
- 7.3 GeV @ 4 pass, 5.5GeV @ 3 Pass and 3.7 GeV @ 2 pass. No five pass beam in the Fall of 2014.
Pre-beam Checklist
Trigger Checkout (Experts)
* Checkout trigger timing * Checkout of EDTM (Barak Schmookler) * Think about adding 60, 100, 150, and 200 ns wide electronic deadtime scalers
- This has been found to be a robust method for determining electronic deadtime in Hall C and we
should think about adding something similar for GMP.