Difference between revisions of "Thursday, Mar. 03: DAY Shift"
From Hall A Wiki
Line 25: | Line 25: | ||
<b>Upcoming event(Long Term)</b> | <b>Upcoming event(Long Term)</b> | ||
* Beam study (Thursday, 3/10) | * Beam study (Thursday, 3/10) | ||
− | * Target boiling test | + | * Target boiling test (60uA) |
Revision as of 10:03, 3 March 2016
Go back to Daily Run Plan Daily Run Plans
- General considerations
Specific mission
- Note: MCC RF recovery (8:30-11:30AM) Down time
1/ Doug: Series of magnet measurement <: 1hr / no beam/ but beam permit
- No controlled access !
Once RF recovery is done,
2/ BCM calibration (high beam current 30uA(60 ideal) with FC & empty target
- Experts will perform this (Dave/Thir/...)
- Calo. HV off
Instruction:
DOC1DOC2
3/ Set up beam through Compton chicane
4/ Production Data with stable beam current
- Detailed instructions here
Upcoming event(Long Term)
- Beam study (Thursday, 3/10)
- Target boiling test (60uA)
BPM/Spot++ Check
- After beam lost for considerable time (like beam study, pass change,...)
- Ask MCC to run 5uA wth carbon hole target and make sure you can see the hole through Spot++