*Updates
 
*Updates
 
**HCal
 
**HCal
 +
***analog sum setup using for cosmics
 +
***DAQ running, can see pulses in data
 +
***still take a day or so to check out everything
 +
***can take cosmics to have things set up as in Test Lab
 +
***software setup
 
**Bigbite Shower
 
**Bigbite Shower
 +
***finished all cabling signal and HV and trigger monitoring, cosmics paddle cabling and labeling
 +
***scalers : all supplies to make the special cables, need to make sure not to forget remove terminator on scaler
 +
***can see signal from the cosmics trigger - cosmics
 +
***mapping check on detector side
 +
***moving from front end to bunker for mapping check - only one mistake found so far
 +
***continue checks and turn one layer at a time and look at individual signals
 +
***HV can be controlled with HV GUI
 +
***cosmics calibration
 +
***Mark set up cosmics trigger, if someone need to use it coordinate with Mark
 +
***cables on table - used to look at trigger rates
 +
***odd thing with scaler rates : sum much higher than individual sum of channels
 +
***Provokar will check offset of the analog fan - to see where the threshold can be set
 +
***Cable for threshold for DAQ - still need to be installed - 50 meters might be long enough for that
 
**Bigbite Hodoscope
 
**Bigbite Hodoscope
 +
***HV just setup thanks to Steve
 +
***LV : were thinking combined voltage with GRINCH but did not work out to have both for GRINCH and hodoscope, so need another supply, Jack ordered another supply
 +
***cabling : need extension on TDC cables - next week
 +
***can start looking at signals straight from PMTs
 +
***all cables laid out
 
**GRINCH
 
**GRINCH
 +
***good progress
 +
***GRINCH fully cables
 +
***HV cables and on
 +
***checking all signals, 3 BNC head need to be fixed for ADC, most signals look good
 +
***powered HV incrementally : most TDC channels are working
 +
***need to replace 2 NINO cards
 +
***some boards cannot reach 5V
 +
***hodoscope using older version
 +
***can use spares - old version found by Rachel - she is shipping it
 +
***checking mapping of detector
 +
***scalers display working in the bunker in bbhodo account
 +
***still need to try to run CODA
 
**LHRS
 
**LHRS
 +
***
 
**CDet
 
**CDet
 
**GEM INFN Test Lab
 
**GEM INFN Test Lab

Revision as of 10:47, 20 August 2021

  • Updates
    • HCal
      • analog sum setup using for cosmics
      • DAQ running, can see pulses in data
      • still take a day or so to check out everything
      • can take cosmics to have things set up as in Test Lab
      • software setup
    • Bigbite Shower
      • finished all cabling signal and HV and trigger monitoring, cosmics paddle cabling and labeling
      • scalers : all supplies to make the special cables, need to make sure not to forget remove terminator on scaler
      • can see signal from the cosmics trigger - cosmics
      • mapping check on detector side
      • moving from front end to bunker for mapping check - only one mistake found so far
      • continue checks and turn one layer at a time and look at individual signals
      • HV can be controlled with HV GUI
      • cosmics calibration
      • Mark set up cosmics trigger, if someone need to use it coordinate with Mark
      • cables on table - used to look at trigger rates
      • odd thing with scaler rates : sum much higher than individual sum of channels
      • Provokar will check offset of the analog fan - to see where the threshold can be set
      • Cable for threshold for DAQ - still need to be installed - 50 meters might be long enough for that
    • Bigbite Hodoscope
      • HV just setup thanks to Steve
      • LV : were thinking combined voltage with GRINCH but did not work out to have both for GRINCH and hodoscope, so need another supply, Jack ordered another supply
      • cabling : need extension on TDC cables - next week
      • can start looking at signals straight from PMTs
      • all cables laid out
    • GRINCH
      • good progress
      • GRINCH fully cables
      • HV cables and on
      • checking all signals, 3 BNC head need to be fixed for ADC, most signals look good
      • powered HV incrementally : most TDC channels are working
      • need to replace 2 NINO cards
      • some boards cannot reach 5V
      • hodoscope using older version
      • can use spares - old version found by Rachel - she is shipping it
      • checking mapping of detector
      • scalers display working in the bunker in bbhodo account
      • still need to try to run CODA
    • LHRS
    • CDet
    • GEM INFN Test Lab
    • RF time
    • HV
    • Scalers
    • EPICS
    • Helicity
    • start / stop / EPICS scripts


  • On-going tasks
    • Network setup ( done ) - SBS MPD side might need few cables - need pull network for SBS side (0%)
    • Scaler crate setup (70 % - Steve ) - Steve could not talk to CPU - IP fixed with DHCP - need change fan tray - CAEN
    • documentation of VME crate names to power cycle - [[1]]- need to make sure all VXS are in dhcp -Bryan
    • 3 rd GEM VXS crate install router moved up ( 100% )
    • need power and network in GEM bunker ( done )
    • boot VME controllers (100 % done - need ask hostname TS crate )
    • TS cables - all fibers plugged - will post informations -hodoscope / grinch/ shower separate - can be combined at any time now everything plugged to TS
    • detector cabling
    • new MPD production - about to start - FPGA shipped to Paolo -
    • MPD VTP readout - on-going in daq lab - still having issue getting APV sending data to MPD - events going through high speed link
    • MPD being setup in Hall A - need setup VTPs to boot (done ) - 10 gigE network plugged (done) - will be able to test in Hall A - LV installed soon (done )
    • setup portservers : 1 4 port portserver for VTP (done), still need to set up a 8 port one and HCAL portserver
    • need to install remote switch for crate in bunker - rest are VXS or VME64 -
    • Bigbite - HCal trigger setup - need check with Bob if additionnal NIM crate need to be install
    • TS setup - 50 %
    • Beamline crate setup ( in scaler crate ) - FADC is in scaler need to be setup - need pull raster BPM BCM (0% will do it with David )
    • HCAL cabling
    • HCAL need power ( done, Berta )
    • Mark hodoscope trigger ?
    • Computer move to Hall A : sbsdaq1/2/3 tedbbdaq (done ) enpcamsonne ( done ) - need to install X server - Need ask Ole -
    • LHRS fiber pull ( waiting fiber August 13th ) - most likely LHRS at end of SBS run
    • Cosmics trigger ( Bogdan ? 0 %) -
    • Cosmics HCAL
    • Cosmics Shower
    • Cosmics Hodoscope
    • Test 10 gig link to DAQ to adaq1
    • EPICS script -
    • alarm handler (David)
  • Outstanding issues
    • 2 bad FADCs Bigbite - 1 FADC was repaired - one being repaired - 1 Compton FADC - repaired can use as spare ( done )
    • SD delay : still need 2 SDs ( Glasgow and INFN just requested quote )
    • need to adjust for HCAL transit time with different PMTs
    • status of cosmics paddles ( installed by Bogdan )
    • GEM fibers too short : Mark will order parts - need to check status of order
    • 15 bad MPDs - need to look at fixing - Ben ? Dustin loaning us 6 MPDs - need 85 total - 67 in hand - 1 MPD (301) VME address issue in some slot -
      • APV needed 1208 - 966 in hand working - Michael might lend 40 - ( check with Thir )
    • GEM fiber possibly bad - 2 broken - if long sleeve want to pull spare in separate conduit
    • GEM HV IP need setup ( Alex ) Done
    • GEM clock/trigger box for BB side