(Created page with "<span style="font-size:larger">'''GMn GEM commissioning Meetings: WEDNESDAY 10:30am - 11:30am'''</span> Link to all previous meetings: [https://hallaweb.jlab.org/wiki/index.p...")
 
(Work plan for GEn-RP)
Line 11: Line 11:
  
 
=== Work plan for GEn-RP ===
 
=== Work plan for GEn-RP ===
1. BBGEM work would start Dec 6th and end Dec 19th. This is the HV upgrades for the UV layers.  
+
# BBGEM work would start Dec 6th and end Dec 19th. This is the HV upgrades for the UV layers.  
2. Transport recoil detector, active analyzer into hall in late Jan. Should happen after re-install of SBS GEMs.
+
# Transport recoil detector, active analyzer into hall in late Jan. Should happen after re-install of SBS GEMs.
3. Remove the SBS GEM stack around Jan 25 for HV upgrades and APV repairs/swaps.
+
# Remove the SBS GEM stack around Jan 25 for HV upgrades and APV repairs/swaps.
4. Work on SBS GEM is 15 days until Feb 15.
+
# Work on SBS GEM is 15 days until Feb 15.
5. Build the SBS GEM bunker after the SBS and HCAL moved into position. This may allow to put the bunker closer.
+
# Build the SBS GEM bunker after the SBS and HCAL moved into position. This may allow to put the bunker closer.
6. Arbitrarily put Joe B installing  the GEM LV supply on Jan 8th. We will continue to use the electronics/LV in place while we upgrade and troubleshoot.
+
# Arbitrarily put Joe B installing  the GEM LV supply on Jan 8th. We will continue to use the electronics/LV in place while we upgrade and troubleshoot.
  
 
=== DAQ updates (Ben, Bryan, Alex) ===
 
=== DAQ updates (Ben, Bryan, Alex) ===
 
*
 
*

Revision as of 14:36, 5 December 2023

GMn GEM commissioning Meetings: WEDNESDAY 10:30am - 11:30am

Link to all previous meetings: GMn GEM Commissioning Meeting

Please use sbs_gems mailing list for plots/communications and HALOG entries relevant to GEMs!


GEM inventory for GEn-RP and GEp:

  • Inventory and plan: [1]
  • HV upgrade tracker: [2]

Work plan for GEn-RP

  1. BBGEM work would start Dec 6th and end Dec 19th. This is the HV upgrades for the UV layers.
  2. Transport recoil detector, active analyzer into hall in late Jan. Should happen after re-install of SBS GEMs.
  3. Remove the SBS GEM stack around Jan 25 for HV upgrades and APV repairs/swaps.
  4. Work on SBS GEM is 15 days until Feb 15.
  5. Build the SBS GEM bunker after the SBS and HCAL moved into position. This may allow to put the bunker closer.
  6. Arbitrarily put Joe B installing the GEM LV supply on Jan 8th. We will continue to use the electronics/LV in place while we upgrade and troubleshoot.

DAQ updates (Ben, Bryan, Alex)