=== Work plan for GEn-RP === | === Work plan for GEn-RP === | ||
# BBGEM work would start Dec 6th and end Dec 19th. This is the HV upgrades for the UV layers. | # BBGEM work would start Dec 6th and end Dec 19th. This is the HV upgrades for the UV layers. | ||
− | * Vimukthi, Holly + techs | + | #* Vimukthi, Holly + techs |
− | * Do we have what we need to do this? | + | #* Do we have what we need to do this? |
# Transport recoil detector, active analyzer into hall in late Jan. Should happen after re-install of SBS GEMs. | # Transport recoil detector, active analyzer into hall in late Jan. Should happen after re-install of SBS GEMs. | ||
− | * Need to upgrade HV on recoil layers and test. Early Jan? | + | #* Need to upgrade HV on recoil layers and test. Early Jan? |
− | * Vimukthi, Bhasitha, Saru, ? | + | #* Vimukthi, Bhasitha, Saru, ? |
# Remove the SBS GEM stack around Jan 25 for HV upgrades and APV repairs/swaps. | # Remove the SBS GEM stack around Jan 25 for HV upgrades and APV repairs/swaps. | ||
− | * Work on SBS GEM is 15 days until Feb 15. | + | #* Work on SBS GEM is 15 days until Feb 15. |
− | * Will we swap modules to put the HV inputs on the same side? | + | #* Will we swap modules to put the HV inputs on the same side? |
− | * What do we need to order now to be ready for this? | + | #* What do we need to order now to be ready for this? |
# Build the SBS GEM bunker after the SBS and HCAL moved into position. | # Build the SBS GEM bunker after the SBS and HCAL moved into position. | ||
− | * Holly will work with engineers and techs, but this will happen maybe Feb timeframe. | + | #* Holly will work with engineers and techs, but this will happen maybe Feb timeframe. |
# Arbitrarily put Joe B installing the GEM LV supply on Jan 8th. We will continue to use the electronics/LV in place while we upgrade and troubleshoot. | # Arbitrarily put Joe B installing the GEM LV supply on Jan 8th. We will continue to use the electronics/LV in place while we upgrade and troubleshoot. | ||
− | * Holly, Vimuthi will coordinate with Joe | + | #* Holly, Vimuthi will coordinate with Joe |
+ | #* Need to verify this week what equipment we need. | ||
=== DAQ updates (Ben, Bryan, Alex) === | === DAQ updates (Ben, Bryan, Alex) === | ||
* | * |
Revision as of 14:41, 5 December 2023
GMn GEM commissioning Meetings: WEDNESDAY 10:30am - 11:30am
Link to all previous meetings: GMn GEM Commissioning Meeting
Please use sbs_gems mailing list for plots/communications and HALOG entries relevant to GEMs!
GEM inventory for GEn-RP and GEp:
Work plan for GEn-RP
- BBGEM work would start Dec 6th and end Dec 19th. This is the HV upgrades for the UV layers.
- Vimukthi, Holly + techs
- Do we have what we need to do this?
- Transport recoil detector, active analyzer into hall in late Jan. Should happen after re-install of SBS GEMs.
- Need to upgrade HV on recoil layers and test. Early Jan?
- Vimukthi, Bhasitha, Saru, ?
- Remove the SBS GEM stack around Jan 25 for HV upgrades and APV repairs/swaps.
- Work on SBS GEM is 15 days until Feb 15.
- Will we swap modules to put the HV inputs on the same side?
- What do we need to order now to be ready for this?
- Build the SBS GEM bunker after the SBS and HCAL moved into position.
- Holly will work with engineers and techs, but this will happen maybe Feb timeframe.
- Arbitrarily put Joe B installing the GEM LV supply on Jan 8th. We will continue to use the electronics/LV in place while we upgrade and troubleshoot.
- Holly, Vimuthi will coordinate with Joe
- Need to verify this week what equipment we need.