Line 1: | Line 1: | ||
*Updates | *Updates | ||
**ECal | **ECal | ||
+ | ***Timeline for installation | ||
+ | ****All PMTs installed this week | ||
+ | ****working on main cable trays from detector to bunker | ||
+ | ****next week main enclosure, can start cabling | ||
+ | ****cosmics by end of October | ||
+ | ****waiting for 39 FADCs end of October | ||
+ | ****Cosmics trigger : self trigger start to look at self trigger like NPS - Hanjie almost done with cosmics trigger firmware | ||
+ | ****ECAL students : Mahmoud VT, Kip UConn ( Simulation + hardware installation ), Jhih-ying (Fadc SCALER ...) UMass ( HCal ) | ||
+ | **** need software for calibration and set VTP thresholds (Jhih-ying ?) | ||
+ | **** long cables from ESB last going in | ||
+ | **** cabling of FADC next week - will connect crate to network and TS when they are done | ||
+ | **** ECAL VTPs put together with SSP - no V1495 in final setup | ||
**HCAL | **HCAL | ||
+ | ***Jiwan and Ji Hing measured delay for VTP and analog - 2.5 uS for new firmware - | ||
+ | ***FADC scalers for HCal being implemented | ||
+ | ***Ben asked David Abbott to update to CODA run control for the sync reset so we can have digital trigger and GEM | ||
+ | *** sync reset enabled in DAQ now - might need to disable if GEM take data - might need to run HCAL , ECAL and GEM separately until CODA update | ||
+ | *** TS crate - but might get single DAQ - | ||
+ | *** HCAL TDC ? : reference time - V1495 output and analog - Trigger time from TS - could put trigger to look at efficiency | ||
**CDet | **CDet | ||
+ | ***CDet moved in Hall A, all 6 modules, frame in 1 or 2 weeks, some things to move from Test Lab | ||
+ | ***Start taking cosmics with full detector readout | ||
+ | ***1 months : cables needed to be made, 3 modules to be retroffited | ||
+ | ***HV : Lecroy crate in HRS - still need two negative HV to use as spare - maybe need 2 more to power the detector | ||
+ | ***CNU students : Jacob, May and Gabriel | ||
+ | *** software : plan to use high resolution software for VETROC | ||
**GEMs | **GEMs | ||
+ | ***arranged fibers on MPD crates | ||
+ | *** will work connecting to VTP and start low level | ||
+ | *** scintillator paddles for cosmics trigger : ~ estimated 1 week for flushing nitrogen + Ar 2nd week of September | ||
+ | *** ordered additionnal fibers | ||
+ | *** LV : could be turned on - using the SBS LV supply - New channels to be installed on break out | ||
+ | *** LV current : need to follow | ||
+ | *** test optical fiber | ||
+ | *** add firmware to MPD for monitoring | ||
+ | *** Histogramming method : ready to be studied - could be compiled for 32 MPDs | ||
+ | *** INFN VTP : check VXS key need to be tighen up | ||
+ | **Beamline | ||
+ | *** to be recabled | ||
+ | *** will ask to Ciprian |
Latest revision as of 11:47, 30 August 2024
- Updates
- ECal
- Timeline for installation
- All PMTs installed this week
- working on main cable trays from detector to bunker
- next week main enclosure, can start cabling
- cosmics by end of October
- waiting for 39 FADCs end of October
- Cosmics trigger : self trigger start to look at self trigger like NPS - Hanjie almost done with cosmics trigger firmware
- ECAL students : Mahmoud VT, Kip UConn ( Simulation + hardware installation ), Jhih-ying (Fadc SCALER ...) UMass ( HCal )
- need software for calibration and set VTP thresholds (Jhih-ying ?)
- long cables from ESB last going in
- cabling of FADC next week - will connect crate to network and TS when they are done
- ECAL VTPs put together with SSP - no V1495 in final setup
- Timeline for installation
- HCAL
- Jiwan and Ji Hing measured delay for VTP and analog - 2.5 uS for new firmware -
- FADC scalers for HCal being implemented
- Ben asked David Abbott to update to CODA run control for the sync reset so we can have digital trigger and GEM
- sync reset enabled in DAQ now - might need to disable if GEM take data - might need to run HCAL , ECAL and GEM separately until CODA update
- TS crate - but might get single DAQ -
- HCAL TDC ? : reference time - V1495 output and analog - Trigger time from TS - could put trigger to look at efficiency
- CDet
- CDet moved in Hall A, all 6 modules, frame in 1 or 2 weeks, some things to move from Test Lab
- Start taking cosmics with full detector readout
- 1 months : cables needed to be made, 3 modules to be retroffited
- HV : Lecroy crate in HRS - still need two negative HV to use as spare - maybe need 2 more to power the detector
- CNU students : Jacob, May and Gabriel
- software : plan to use high resolution software for VETROC
- GEMs
- arranged fibers on MPD crates
- will work connecting to VTP and start low level
- scintillator paddles for cosmics trigger : ~ estimated 1 week for flushing nitrogen + Ar 2nd week of September
- ordered additionnal fibers
- LV : could be turned on - using the SBS LV supply - New channels to be installed on break out
- LV current : need to follow
- test optical fiber
- add firmware to MPD for monitoring
- Histogramming method : ready to be studied - could be compiled for 32 MPDs
- INFN VTP : check VXS key need to be tighen up
- Beamline
- to be recabled
- will ask to Ciprian
- ECal