Difference between revisions of "Polhe3 meeting 20120418"
From Hall A Wiki
(New page: * progress ** after checking optics, Boris polarization is still low and dropping. see [http://hallaweb.jlab.org/equipment/targets/polhe3/lab/jie/Boris/Boris.pdf] ** finished AFP loss test...) |
|||
(10 intermediate revisions by the same user not shown) | |||
Line 5: | Line 5: | ||
* todo | * todo | ||
*** Use the Moss cell to check system again. | *** Use the Moss cell to check system again. | ||
− | **** masing effect for Moss cell ( polarization ~ 20%), details see [http://hallaweb.jlab.org/equipment/targets/polhe3/lab/jie/Moss/Moss_spin_up.GIF] and [http:// | + | **** masing effect for Moss cell ( polarization ~ 20%), details see [http://hallaweb.jlab.org/equipment/targets/polhe3/lab/jie/Moss/Moss_spin_up.GIF] and [http://hallaweb.jlab.org/equipment/targets/polhe3/lab/jie/Moss/EPR_AFP_20120422_1144.htm] |
**** set up the gradient coil | **** set up the gradient coil | ||
**** test different currents and thresholds | **** test different currents and thresholds | ||
Line 11: | Line 11: | ||
*** if system OK. we will do following (2 weeks):temperature optimization and diffusion test (225~240, may add point 220) | *** if system OK. we will do following (2 weeks):temperature optimization and diffusion test (225~240, may add point 220) | ||
**** temperature stabilized ~ 4 hours | **** temperature stabilized ~ 4 hours | ||
− | **** spin up | + | **** spin up. Note: |
+ | ***** field sweep | ||
+ | ***** 12sweep * 2 hours ( if spin up time > 6hours), | ||
+ | ***** 15sweep * 1 hours ( if spin up time < 6hours) | ||
**** do EPR | **** do EPR | ||
− | **** do internal temperature test | + | **** do internal temperature test. Note: |
− | **** do AFP loss with laser on, check immediately | + | ***** do NMR field sweep: laser on - off - on - off- on, each time temperature should be stabilized, ~ 20min), total: 1.5 hour |
− | **** do diffusion model ~ | + | **** do AFP loss with laser on( '''do both field sweep and freq sweep''', temperature stabilized) |
− | **** wait for another 3~6 | + | ***** do NMR field sweep 5~10 sweeps, check immediately,if not stable, should use 10 sweeps.Note: |
− | **** do AFP loss with laser off, check immediately | + | ***** then do NMR freq sweep 5~ 10 sweeps, check immediately,if not stable, should use 10 sweeps. |
− | **** do hot spin-down ~ | + | ***** '''then do one field sweep- do one frequency sweep - do one field sweep - do one frequency sweep - do one field sweep- do one freq sweep, when begin to measure, click on loaddata, no need to change phase now'''. |
+ | ***** purpose: to get the signal ratio of FIELD SWEEP/FREQ SWEEP, to do cross calibration ( EPR and water calibration) | ||
+ | **** do diffusion model ~ 6 hours. Note: | ||
+ | ***** '''it is better to use field sweep for diffusion, click loaddata when run the program''' | ||
+ | ***** 37 sweep *10 min | ||
+ | **** wait for another 3~6 hour( polarization is become stable),or we can put it in diffusion test. | ||
+ | ***** purpose: it depends on the results of destroying polarization, if polarization is high and stable, we can ignore this step. | ||
+ | **** do AFP loss with laser off, using field sweep( temperature stabilized, 5~ 10 sweeps),check immediately | ||
+ | **** do hot spin-down, field sweep ~ 10 sweep * 2 hours | ||
**** do one cold spin down for this cell after finishing all temperature tests ~18 hours | **** do one cold spin down for this cell after finishing all temperature tests ~18 hours | ||
+ | **** have any question about above procedures, please call me (Jie: 434-327-7584). | ||
Latest revision as of 01:13, 1 May 2012
- progress
- todo
- Use the Moss cell to check system again.
- if system OK. we will do following (2 weeks):temperature optimization and diffusion test (225~240, may add point 220)
- temperature stabilized ~ 4 hours
- spin up. Note:
- field sweep
- 12sweep * 2 hours ( if spin up time > 6hours),
- 15sweep * 1 hours ( if spin up time < 6hours)
- do EPR
- do internal temperature test. Note:
- do NMR field sweep: laser on - off - on - off- on, each time temperature should be stabilized, ~ 20min), total: 1.5 hour
- do AFP loss with laser on( do both field sweep and freq sweep, temperature stabilized)
- do NMR field sweep 5~10 sweeps, check immediately,if not stable, should use 10 sweeps.Note:
- then do NMR freq sweep 5~ 10 sweeps, check immediately,if not stable, should use 10 sweeps.
- then do one field sweep- do one frequency sweep - do one field sweep - do one frequency sweep - do one field sweep- do one freq sweep, when begin to measure, click on loaddata, no need to change phase now.
- purpose: to get the signal ratio of FIELD SWEEP/FREQ SWEEP, to do cross calibration ( EPR and water calibration)
- do diffusion model ~ 6 hours. Note:
- it is better to use field sweep for diffusion, click loaddata when run the program
- 37 sweep *10 min
- wait for another 3~6 hour( polarization is become stable),or we can put it in diffusion test.
- purpose: it depends on the results of destroying polarization, if polarization is high and stable, we can ignore this step.
- do AFP loss with laser off, using field sweep( temperature stabilized, 5~ 10 sweeps),check immediately
- do hot spin-down, field sweep ~ 10 sweep * 2 hours
- do one cold spin down for this cell after finishing all temperature tests ~18 hours
- have any question about above procedures, please call me (Jie: 434-327-7584).
- Calendar
timeline | Tasks | To be done by | status | |
---|---|---|---|---|
new cell | ||||
04/18-05/02 | receiving from UVa | Jie and Zhiwen | ||
oven bottom piece | ||||
04/18-05/02 | design and make oven bottom piece | Zhiwen and Yawei | ||
04/24-04/27 | set up gradient coil and test | Yawei and Jie | ||
diffusion model measurement | ||||
04/27-05/09 | do the test | all | ||
Dominic test | ||||
05/09-05/19 | set up the comet laser and do the test | all | ||
pulse NMR | ||||
05/19-? | pNMR setup and test | Jie |