Difference between revisions of "Meeting 2023 12 06"
From Hall A Wiki
(Created page with "<span style="font-size:larger">'''GMn GEM commissioning Meetings: WEDNESDAY 10:30am - 11:30am'''</span> Link to all previous meetings: [https://hallaweb.jlab.org/wiki/index.p...") |
(→Work plan for GEn-RP) |
||
(4 intermediate revisions by the same user not shown) | |||
Line 11: | Line 11: | ||
=== Work plan for GEn-RP === | === Work plan for GEn-RP === | ||
− | + | # BBGEM work would start Dec 6th and end Dec 19th. This is the HV upgrades for the UV layers. | |
− | + | #* Vimukthi, Holly, Xinzhan, Saru + techs | |
− | + | #* Do we have what we need to do this? | |
− | + | #* Replace APVs? | |
− | + | # Transport recoil detector, active analyzer into hall in late Jan. Should happen after re-install of SBS GEMs. | |
− | + | #* Need to upgrade HV on recoil layers and test. Early Jan? | |
+ | #* Vimukthi, Bhasitha, Saru, ? | ||
+ | # Remove the SBS GEM stack around Jan 25 for HV upgrades and APV repairs/swaps. | ||
+ | #* Work on SBS GEM is 15 days until Feb 15. | ||
+ | #* Will we swap modules to put the HV inputs on the same side? | ||
+ | #* What do we need to order now to be ready for this? | ||
+ | # Build the SBS GEM bunker after the SBS and HCAL moved into position. | ||
+ | #* Holly will work with engineers and techs, but this will happen maybe Feb timeframe. | ||
+ | # Arbitrarily put Joe B installing the GEM LV supply on Jan 8th. We will continue to use the electronics/LV in place while we upgrade and troubleshoot. | ||
+ | #* Holly, Vimuthi will coordinate with Joe | ||
+ | #* Need to verify this week what equipment we need. | ||
=== DAQ updates (Ben, Bryan, Alex) === | === DAQ updates (Ben, Bryan, Alex) === | ||
* | * |
Latest revision as of 11:35, 6 December 2023
GMn GEM commissioning Meetings: WEDNESDAY 10:30am - 11:30am
Link to all previous meetings: GMn GEM Commissioning Meeting
Please use sbs_gems mailing list for plots/communications and HALOG entries relevant to GEMs!
GEM inventory for GEn-RP and GEp:
Work plan for GEn-RP
- BBGEM work would start Dec 6th and end Dec 19th. This is the HV upgrades for the UV layers.
- Vimukthi, Holly, Xinzhan, Saru + techs
- Do we have what we need to do this?
- Replace APVs?
- Transport recoil detector, active analyzer into hall in late Jan. Should happen after re-install of SBS GEMs.
- Need to upgrade HV on recoil layers and test. Early Jan?
- Vimukthi, Bhasitha, Saru, ?
- Remove the SBS GEM stack around Jan 25 for HV upgrades and APV repairs/swaps.
- Work on SBS GEM is 15 days until Feb 15.
- Will we swap modules to put the HV inputs on the same side?
- What do we need to order now to be ready for this?
- Build the SBS GEM bunker after the SBS and HCAL moved into position.
- Holly will work with engineers and techs, but this will happen maybe Feb timeframe.
- Arbitrarily put Joe B installing the GEM LV supply on Jan 8th. We will continue to use the electronics/LV in place while we upgrade and troubleshoot.
- Holly, Vimuthi will coordinate with Joe
- Need to verify this week what equipment we need.