=== Work plan for GEn-RP ===
 
=== Work plan for GEn-RP ===
 
# BBGEM work would start Dec 6th and end Dec 19th. This is the HV upgrades for the UV layers.  
 
# BBGEM work would start Dec 6th and end Dec 19th. This is the HV upgrades for the UV layers.  
 +
#* Vimukthi, Holly, Xinzhan, Saru + techs
 +
#* Do we have what we need to do this?
 +
#* Replace APVs?
 
# Transport recoil detector, active analyzer into hall in late Jan. Should happen after re-install of SBS GEMs.
 
# Transport recoil detector, active analyzer into hall in late Jan. Should happen after re-install of SBS GEMs.
 +
#* Need to upgrade HV on recoil layers and test. Early Jan?
 +
#* Vimukthi, Bhasitha, Saru, ?
 
# Remove the SBS GEM stack around Jan 25 for HV upgrades and APV repairs/swaps.
 
# Remove the SBS GEM stack around Jan 25 for HV upgrades and APV repairs/swaps.
# Work on SBS GEM is 15 days until Feb 15.
+
#* Work on SBS GEM is 15 days until Feb 15.
# Build the SBS GEM bunker after the SBS and HCAL moved into position. This may allow to put the bunker closer.
+
#* Will we swap modules to put the HV inputs on the same side?
 +
#* What do we need to order now to be ready for this?
 +
# Build the SBS GEM bunker after the SBS and HCAL moved into position.
 +
#* Holly will work with engineers and techs, but this will happen maybe Feb timeframe.
 
# Arbitrarily put Joe B installing  the GEM LV supply on Jan 8th. We will continue to use the electronics/LV in place while we upgrade and troubleshoot.
 
# Arbitrarily put Joe B installing  the GEM LV supply on Jan 8th. We will continue to use the electronics/LV in place while we upgrade and troubleshoot.
 +
#* Holly, Vimuthi will coordinate with Joe
 +
#* Need to verify this week what equipment we need.
  
 
=== DAQ updates (Ben, Bryan, Alex) ===
 
=== DAQ updates (Ben, Bryan, Alex) ===
 
*
 
*

Latest revision as of 11:35, 6 December 2023

GMn GEM commissioning Meetings: WEDNESDAY 10:30am - 11:30am

Link to all previous meetings: GMn GEM Commissioning Meeting

Please use sbs_gems mailing list for plots/communications and HALOG entries relevant to GEMs!


GEM inventory for GEn-RP and GEp:

  • Inventory and plan: [1]
  • HV upgrade tracker: [2]

Work plan for GEn-RP

  1. BBGEM work would start Dec 6th and end Dec 19th. This is the HV upgrades for the UV layers.
    • Vimukthi, Holly, Xinzhan, Saru + techs
    • Do we have what we need to do this?
    • Replace APVs?
  2. Transport recoil detector, active analyzer into hall in late Jan. Should happen after re-install of SBS GEMs.
    • Need to upgrade HV on recoil layers and test. Early Jan?
    • Vimukthi, Bhasitha, Saru, ?
  3. Remove the SBS GEM stack around Jan 25 for HV upgrades and APV repairs/swaps.
    • Work on SBS GEM is 15 days until Feb 15.
    • Will we swap modules to put the HV inputs on the same side?
    • What do we need to order now to be ready for this?
  4. Build the SBS GEM bunker after the SBS and HCAL moved into position.
    • Holly will work with engineers and techs, but this will happen maybe Feb timeframe.
  5. Arbitrarily put Joe B installing the GEM LV supply on Jan 8th. We will continue to use the electronics/LV in place while we upgrade and troubleshoot.
    • Holly, Vimuthi will coordinate with Joe
    • Need to verify this week what equipment we need.

DAQ updates (Ben, Bryan, Alex)