− | + | Go back to Daily Run Plan [[Daily Run Plans]] | |
+ | |||
+ | ** Julie note from Beam Team Meeting at 1:30PM, Mar.8, 2016 at MCC. | ||
* <b>Purpose</b>: Plans to run at 60uA | * <b>Purpose</b>: Plans to run at 60uA | ||
Line 23: | Line 25: | ||
- 2/ High current 60 uA should be deliverable for calibration and production both 4pass and 5pass | - 2/ High current 60 uA should be deliverable for calibration and production both 4pass and 5pass | ||
− | * <b>Concluded Plan</b>: Try 60 uA Thursday morning up to noon | + | * <b>Concluded Plan</b>: |
+ | - Try 60 uA Thursday morning up to noon |
Latest revision as of 18:07, 8 March 2016
Go back to Daily Run Plan Daily Run Plans
- Julie note from Beam Team Meeting at 1:30PM, Mar.8, 2016 at MCC.
- Purpose: Plans to run at 60uA
- Current issues:
- There is no consensus on why the beam is limited at 30 uA.
- Ideas:
- 1/ The limitation is in the injector - 2/ In the RF separator
- Attempt:
- 1/ Removing/Changing Wien filter (horizontal-> vertical) ?? - 2/ Run with a magnetic separation ??
- Problem foresee:
- 1/ ?? - 2/ Compatible with Hall D taking data
- GMp expert inform:
- 1/ Polarization is not matter - 2/ High current 60 uA should be deliverable for calibration and production both 4pass and 5pass
- Concluded Plan:
- Try 60 uA Thursday morning up to noon