Difference between revisions of "Thursday, May 11, 2017 11:00am ET"
From Hall A Wiki
(→Minutes) |
|||
Line 24: | Line 24: | ||
** Ernie looked over the location to check electrical power/water cooling | ** Ernie looked over the location to check electrical power/water cooling | ||
* Future work (recommendations from review - not ready) | * Future work (recommendations from review - not ready) | ||
− | ** | + | ** collimator/shielding - Tyler |
− | * JLAB contract | + | *** ds petal is "only" a cleanup collimator |
+ | *** ds petal generates backgrounds - doesn't have to be right against the nose | ||
+ | *** going to move it as far upstream as possible - radiation on hybrid nose will go down by reduced solid angle | ||
+ | *** Cameron is working on the simulations | ||
+ | * JLAB contract (end of May) - finish the cigar collimator design | ||
+ | ** we're in extension now - need a new contract | ||
+ | *** describe deliverables from old, define activities for new | ||
** quality control/testing for prototype | ** quality control/testing for prototype | ||
+ | ** upstream cigar collimator | ||
+ | *** water-cooling/thermal was part of old contract | ||
+ | *** manufacturing/motion/supports in new | ||
+ | ** Prototype | ||
+ | *** old contract deliverable was getting bids | ||
+ | *** new contract is time from MIT for construction/quality control, testing | ||
+ | ** Downstream toroid | ||
+ | *** test prototype coil before going forward | ||
+ | *** failure mode analysis? | ||
+ | |||
+ | |||
* Next meeting time | * Next meeting time | ||
Revision as of 11:30, 11 May 2017
Last meeting: Monday, March 20, 2017 3:00pm EST
Agenda
- Prototype coil
- Future work (recommendations from review - not ready)
- JLAB contract
- Next meeting time
Minutes
Attending: Juliette, Seamus, KK, Jim, Jason, Ernie
- Prototype coil
- in contact with Emerson
- almost done
- waiting for final quote
- Ernie looked over the location to check electrical power/water cooling
- Future work (recommendations from review - not ready)
- collimator/shielding - Tyler
- ds petal is "only" a cleanup collimator
- ds petal generates backgrounds - doesn't have to be right against the nose
- going to move it as far upstream as possible - radiation on hybrid nose will go down by reduced solid angle
- Cameron is working on the simulations
- collimator/shielding - Tyler
- JLAB contract (end of May) - finish the cigar collimator design
- we're in extension now - need a new contract
- describe deliverables from old, define activities for new
- quality control/testing for prototype
- upstream cigar collimator
- water-cooling/thermal was part of old contract
- manufacturing/motion/supports in new
- Prototype
- old contract deliverable was getting bids
- new contract is time from MIT for construction/quality control, testing
- Downstream toroid
- test prototype coil before going forward
- failure mode analysis?
- we're in extension now - need a new contract
- Next meeting time