(Friday Oct 1 Swing and Oct 2 Owl)
Line 1: Line 1:
 
Back to [[DVCS]]
 
Back to [[DVCS]]
 +
 +
 +
 +
 +
 +
[[http://www.jlab.org/~adaq/halog/html/1010_archive/101010175128.html  Run Plan for Swing 10/10 through Day 10/11]]
 +
 +
 +
 +
  
 
[[ Start up run plan]]: plans for the very beginning of the data taking, data that can be taken without LHRS and cryo target.
 
[[ Start up run plan]]: plans for the very beginning of the data taking, data that can be taken without LHRS and cryo target.

Revision as of 18:14, 10 October 2010

Back to DVCS



[Run Plan for Swing 10/10 through Day 10/11]



Start up run plan: plans for the very beginning of the data taking, data that can be taken without LHRS and cryo target.


Friday Oct 1 Swing and Oct 2 Owl

  1. Check beam on target (experts will do this)
  2. Lumi tests (Kalyan will do this: page number 357-1057)
  3. Compton rates with laser and beam scan (Eric will lead this study in the backroom)
  4. While Compton study takes place, take HRS cosmics data (CODA configuration: LeftHRS). Replay the data and page expert if something looks wrong
  5. BPM calibration
  6. Raster calibration
  7. Go to empty target (you should already be there!), and call MCC to let them know we don't want beam anymore (they will run some tests of their own then). You're free to go...

In case of problems, page Carlos (584-0049) or call Run Coordinator.