(Created page with "<span style="font-size:larger">'''GMn GEM commissioning Meetings: WEDNESDAY 10:30am - 11:30am'''</span> Link to all previous meetings: [https://hallaweb.jlab.org/wiki/index.p...") |
(→Update on BB GEMs) |
||
Line 21: | Line 21: | ||
=== Update on BB GEMs === | === Update on BB GEMs === | ||
− | * | + | * All APVs plugged in and working. |
+ | * Will perform a pedestal analysis soon. | ||
+ | ** Waiting for HiVolta supply to evaluate pedestals on layer 0. | ||
=== Common Mode Algorithms === | === Common Mode Algorithms === |
Revision as of 10:10, 25 May 2022
GMn GEM commissioning Meetings: WEDNESDAY 10:30am - 11:30am
Link to all previous meetings: GMn GEM Commissioning Meeting
Please use sbs_gems mailing list for plots/communications and HALOG entries relevant to GEMs!
Contents
Near term work plan
- See installation plan for SBS here: plan
- Installation of HV dividers on BB: work plan
- Thoughts on special run requests during GEn:
- Luminosity studies (Nilanga)
- Full readout studies for negative pulse studies and etc (Sean)
Update on INFN GEM layers for GEn-RP
- Layers assembled and ready to be inserted in inline stack. Plan to run up HV this week.
Update on UVa GEM layers for GEn-RP
Update on BB GEMs
- All APVs plugged in and working.
- Will perform a pedestal analysis soon.
- Waiting for HiVolta supply to evaluate pedestals on layer 0.
Common Mode Algorithms
DAQ updates (Ben, Bryan, Alex)
- schematic of setup?
- FIR filter?
- Update on: need 2 DC working in Hall A