Polhe3 meeting 20120418
From Hall A Wiki
- progress
- todo
- Use the Moss cell to check system again.
- if system OK. we will do following (2 weeks):temperature optimization and diffusion test (225~240, may add point 220)
- temperature stabilized ~ 4 hours
- spin up ~ 24 hours
- do EPR
- do internal temperature test (do NMR laser on - off - on)~ 1 hour
- do AFP loss with laser on, check immediately
- do diffusion model ~ 4 hours
- wait for another 3~6 hours, or we can put it in diffusion test.
- do AFP loss with laser off, check immediately
- do hot spin-down ~ 12 hours
- do one cold spin down for this cell after finishing all temperature tests ~18 hours
- Calendar
timeline | Tasks | To be done by | status | |
---|---|---|---|---|
new cell | ||||
04/18-05/02 | receiving from UVa | Jie and Zhiwen | ||
oven bottom piece | ||||
04/18-05/02 | design and make oven bottom piece | Zhiwen and Yawei | ||
04/24-04/27 | set up gradient coil and test | Yawei and Jie | ||
diffusion model measurement | ||||
04/27-05/09 | do the test | all | ||
Dominic test | ||||
05/09-05/19 | set up the comet laser and do the test | all | ||
pulse NMR | ||||
05/19-? | pNMR setup and test | Jie |