GMn GEM commissioning Meetings: WEDNESDAY 10:30am - 11:30am
Link to all previous meetings: GMn GEM Commissioning Meeting
Please use sbs_gems mailing list for plots/communications and HALOG entries relevant to GEMs!
GEM inventory for GEn-RP and GEp:
Work plan for GEn-RP
- BBGEM work would start Dec 6th and end Dec 19th. This is the HV upgrades for the UV layers.
- Transport recoil detector, active analyzer into hall in late Jan. Should happen after re-install of SBS GEMs.
- Remove the SBS GEM stack around Jan 25 for HV upgrades and APV repairs/swaps.
- Work on SBS GEM is 15 days until Feb 15.
- Build the SBS GEM bunker after the SBS and HCAL moved into position. This may allow to put the bunker closer.
- Arbitrarily put Joe B installing the GEM LV supply on Jan 8th. We will continue to use the electronics/LV in place while we upgrade and troubleshoot.