Wednesday, October 9, 2013 2:00pm EST
From Hall A Wiki
Last group meeting: Wednesday, June 12, 2013 10:30am EST
Last meeting: Monday, October 7, 2013 2:00pm EST
Agenda
These presentations may be updated right before the meeting
- Status of the engineering work
- Update from Jason on support structure .pptx .pdf
backup:
presentation from June
Tyler's interference slides - Update from Jim on vacuum vessel .pptx .pdf
- Update from Jason on support structure .pptx .pdf
- Update on the physics/optics work
Minutes
Attending: Juliette, Robin, Stanley, Jim, Jason, Jay, Kent, KK, Thia, Javier
- Status of the engineering work
- Update from Jason on support structure
- green and blue are Al strongbacks; pink blocks are Al with coil
- slide 7 doesn't include bolted connections
- Slide 9 Questions:
Could top piece be an I-beam? - Needs strength in both directions.
Is this assembly made and then assembled? - yes - coil is pre-assembled with carrier.
- Update from Jim on vacuum vessel
- Update from Jason on support structure
- Update on the physics/optics work
- Update from Juliette on iron simulations